BRIEF ON
DROUGHT AFFECTED AREAS
THAR, KOHISTAN AND KACHHO
AREAS OF SINDH PROVINCE
INTRODUCTION
Relief For The Drought Affected People Of The
Desert Area Of Thar And Arid Zone Of Kohistan
BASIC FACTS
The Thar region of Sindh is the largest desert area of Sindh with sub-Saharan conditions. It extends from the coastal area of the Runn and Kutch along the southern border with India to Sukkur covering an area of 19000 square kilometers. Kohistan area starts from the north of Karachi and moves along to Balochistan. The total area of this region is about 13,000 square kilometers. The following are some of the basic facts:
LOSSES
The Government of Sindh started its relief operations in September 1999 to provide emergent relief to the drought affected areas even before it started adversely affecting the people in the Thar region. Immediate measures were taken to strengthen logistics support, provide drinking water and materail supplies and extend the relief cover to a large part of the affceted area. The support already provided includes:
In order to alleviate the sufferings of drought affectees, a Full Scale Emergency relief Plan has also been prepared initially for tow months.
The Plan consists of a major thrust to continue and upscale the existing activities and cover the entire affected region. The Emergency Plan therefore, comprises of 5 main components, namely:
Summary is at Annexure "C"
LONG TERM PLAN
A three pronged strategy to make the benefits of the plan to flow to the common persons.
ROAD SECTOR
Ongoing schemes completion cost Rs. 336.835 Million
(Thar and Umerkot)
New schemes (Thar and Umerkot) Rs. 1578.000 Million
New schemes (Dadu and Thatta) Rs. 987.000 Million
New schemes Rs. 1095.992 Million
Grand Total Rs. 3997.827 Million
THAR REGION
|
|
|
|
Affected |
|
| Tharparkar |
159
(166)* |
1895
(2085)** |
0.89
(million) |
3.00
(million) |
| Umerkot |
25
(234)* |
316
(1066)** |
0.15
(million) |
1.00
(million) |
KOHISTAN/KACHHO AREA
|
|
|
|
Affected |
|
| Dadu |
35
(525)* |
453
(4420)** |
0.26
(million) |
1.00
(million) |
| Total |
219
|
2664
|
1.30
(million) |
5.00
(million) |
Note:
| Nature of Relief | Financial Implication in
THAR region |
Financial Implication in Kohistan/ Kachho Area |
| Past year Government dues for one year |
Rs. 4.00 (million)
|
Rs. 0.23 (million)
|
| Remission of Land Revenue and Cesses |
Rs. 2.00 (million)
|
Rs. 0.05 (million)
|
| Wheat provided at the subsidized rate of Rs. 5/-Per kg @ 20 kg/family/per month) |
Rs. 20.00 (million)
|
Rs. 25.00 (million)
|
| Food items distribution in Sep/Oct 1999 |
Rs. 6.60 (million)
|
|
| Cash grant for purchase of Food ration, fodder etc. |
Rs. 190.00 (million)
|
Rs. 25.00 (million)
|
| Pilot Lungar Project |
Rs. 1.00 (million)
|
|
| Total |
Rs. 223.60 (million)
|
Rs. 50.28 (million)
|
| Grand Total |
Rs. 273.88 (million)
|
|
|
|
KACHHO |
| 1. Free distribution of
ration items including transportation charges) Annexed at (C1-3) |
Rs. 720.00 (million)
|
Rs. 144.0 (million)
|
| 2. Processed feed (fodder) annexed at C-4 |
Rs. 300.00 (million)
|
Rs. 25.0 (million)
|
| 3. a) Digging of wells for supply
of drinking water
b) Repair and maint- enance of SAZDA tube wells for
|
Rs. 22.0 (million)
Rs. 20.0 (million) |
Rs. 3.0 (million)
Rs. 5.0 (million) |
| 4. Logistic Support annexed at C-6 |
Rs. 10.0 (million)
|
Rs. 2.0 (million)
|
| 5. Medicine/health*
cover (human lives) annexed at C-7 |
Rs. 350.0 (million)
|
Rs. 10.0 (million)
|
| 6. Veterinary cover/
medicines annexed at C-8 |
Rs. 22.0 (million)
|
Rs. 8.0 (million)
|
| Total |
Rs. 1,444.0 (million)
|
Rs. 197.0 (million)
|
| Grand Total |
Rs. 1,641.0 (million)
|
DISTRICT THAR AND UMERKOT
#
Name of Scheme
Cost in Million
Fund required for for completion
Target
of the Schemes
during 2000-2001
--------------------------------------------------------------------------------------------------------------------------------
1. Const: of Road from Umerkot Rs. 200.38
62.766
100%
to Chachro via Kantio (69kms)
2. Const: of Road from Umerkot Rs. 108.217
100.856
100%
to Chachro via Ratnour (100kms)
3. Const: of Road from Mithi
Rs. 94.881
21.000
100%
to Islamkot (32kms)
4. Const: of Road from Diplo
Rs. 160.952
104.413
100%
to Islamkot (70 kms)
5. Const: of Road from Diplo
Rs. 121.088
47.800
100%
to Ali Bunder (60 kms)
--------------- -----------------
TOTAL:- A) RS. 685.518 RS. 336.835
--------------- -----------------
By construction of the following new roads, it will create job opportunities
for the people of the project areas, resulting in employment of man power
999,000 man-months. This will also minimize the migration trained during
drought condition and enhance the prosperity of the people.
B - NEW ROAD SECTOR SCHEMES:
DISTRICT THAR AND UMERKOT TOTAL COST PROJECT PERIOD
1. Const: of Road from Jalo-jo-Chaunro
Rs. 93.00 Mil.
3 Years
to Rantnour (31kms)
2. Const: of Road from Chachro
Rs. 66.00 "
-do-
to Mubarak-jo-Tar (20kms)
3. Const: of Road Chachro
Rs. 118.00 "
-do-
to Khensar (36 kms)
4. Const: of Road Khensar
Rs. 132.00 "
-do-
to Ratnour (40 kms)
5. Const: of Road Chachro
Rs. 132.00 "
-do-
to Ratnour via Virari (40 kms)
6. Const: of Road Chelhar
Rs. 79.00 "
-do-
to Kantio (24 kms)
7. Const: of Road Islamkot to
Rs. 244.00 "
5 years
Nagarparkar via Virawah (105 kms)
8. Const: of Road Wango to
Rs. 158.00 "
3 years
Diplo via Khetlari (48 kms)
9. Const: of Road Naukot to
Rs. 181.00 "
3 Years
Dilpo (55 kms)
10. Const: of Road Chachro to
Rs. 363.00 "
5 Years
Virawah via Dano Dhandal (110 kms)
---------------------------- -----------------
TOTAL Kms 478 TOTAL:- B) RS. 1,578.00 "
---------------------------- -----------------
DADU AND THATTA DISTRICT TOTAL COST PROJECT PERIOD
1. Const: of Road from Tong Sharif
Rs. 90.00 Mil.
3 Years
to Karchat (30kms)
2. Const: of Road from Mole
Rs. 78.00 "
-do-
to Sari (26kms)
3. Const: of Road Wahi Pandhi
Rs. 75.00 "
-do-
to Chinni (25kms)
4. Const: of Road Thano Ahmad Khan
Rs. 105.00 "
-do-
to Thano Arab Khan (35 kms)
5. Const: of Road Dhamach
Rs. 75.00 "
-do-
to Sari (25kms)
6. Const: of Road Thano Ahmad Khan
Rs. 216.00 "
4 Years
to Toung Sharif via Ali Murad Bareio(72kms)
7. Const: of Road Thano Ahmad Khan
Rs. 189.00 "
-do-
to Karchat via Thano Arab Khan (63kms)
8. Const: of Road Jungshahi to
Rs. 84.00 "
2 Years
Malmari (28kms)
9. Const: of Road Malmari to
Rs. 75.00 "
-do-
to Super Highway (25kms)
---------------------------- -----------------
TOTAL Kms 329 TOTAL:- C) RS. 987.00 "
---------------------------- -----------------
G. TOTAL FOR ON-GOING (A+B+C):- RS. 2,902.00 "
AND NEW PROPOSEDSCHEMES PACKAGE
-----------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------
NO. Water Sector
PROJECT
TIME PERIOD
RMKS:
---------------------------------------------------------------------------------------------------------------------
1. Drilling/Installation of
Rs. 15.000
12 months PC-I submitted to P&D Deptt.
10 Nos Tube Wells in Kohistan Region
2. Constructing Delay Action
Rs. 29.845
24 months
Concept clearn.
Dams, Small Dams, Recharge
paper attached.
Gabion Dams in (upper Kohistan)
PC-I prepared in
1990-93
3. Constructing Delay Action
Rs. 161.969
36 months
-do-
Dams, Small Dams, Recharge
Gabion Dams in (lower Kohistan)
4. Constructing Delay Action
Rs. 98.828
20 months
-do-
Dams, Small Dams, Recharge
Gabion Dams in (Central Kohistan)
5. Constructing of 15 Nos Recharge
Rs. 24.950
12 months
-do-
Gabion-Dam in N.P.Kar area of
Thar Region in Sindh Arid Zone
6. Drinking Water Supply through
Rs. 55.000
-do-
-do-
Pipe line from Pokhan Dhoro to
Surrounding villages (25 Kms)
7. Drinking Water Supply through
Rs. 14.200
-do-
-do-
Pipe line from Parche-ji-Wari to
Dudhrio (07 Kms)
8. Drinking Water Supply through
Rs. 161.000
24 months
-do-
Pipe line from Umerkot to Jalo-
Chanro and adjoining village (70 Kms)
9. Introduction of Drip Irrigation
Rs. 10.000
12 months
--
System in Thar and Kohistan Region
10. Community Based cactus
Rs. 15.000
36 months
-
plantations in Arid Zone of
Sindh
11. Drilling/Installation of
Rs. 98.750
24 months
Concept clearn.
50 Nos Tube Wells
paper attached
in Thar Region (Northern Thar)
PC-I Prepared
(through hired Rigs)
1990-93
12. Drilling/Installation of
Rs. 98.750
-do-
-do-
50 Nos Tube Wells in
Thar Region (Southern Thar)
(through hired Rigs)
13. Drilling/Installation of
Rs. 98.750
-do-
-do-
50 Nos Tube Wells in
Koh: Region (Lower Kohistan)
14. Drilling/Installation of
Rs. 90.000
-do-
-do-
50 Nos Tube Wells in
Koh: Region (Upper Kohistan)
(through hired Rigs)
15. Drilling/Installation of
Rs. 98.750
-do-
-do-
50 Nos Tube Wells in
Koh: Region (Central Kohistan)
(through hired Rigs)
16. Feasibility Study for Construction
Rs. 15.000
12 months
-do-
of Gaj Dam for drinking &
Irrigation purposes in Kohistan Region
17. Feasibility Study of Thar Canal Rs. 10.000 12 months -do-
-----------------
TOTAL: RS. 1,095.992
-----------------