MAINTAINING BIODIVERSITY IN PAKISTAN WITH
RURAL COMMUNITY DEVELOPMENT
REPORT OF THE INDEPENDENT EVALUATION/FORMULATION MISSION
APRIL 1997
Keith Garratt
Michael Murphree
Kalimullah Shirazi
CONTENTS
ABBREVIATIONS AND ACRONYMS
EXECUTIVE SUMMARY
PART I
PROJECT EVALUATION
1. INTRODUCTION
1.1 Background and Purpose of mission
1.2 Mission team
1.3 Itinerary
2. PROJECT CONCEPT AND DESIGN
2.1 Objectives
2.2 Implementation Arrangements
2.3 Proposed Outputs and Actions
3. ACTIVITIES AND ACHIEVEMENTS
3.1 Contribution to Policy and Legislation Development
3.2 Identification of Project Valleys
3.3 Rapid Assessments of Biodiversity
3.4 Geographical Coverage
3.5 Ecosystem Coverage
3.6 Species Coverage
3.7 Participatory Rural Appraisals (PRA)
3.8 Village Management Plans
3.8.1 Overview
3.8.2 The Development of VMPs In The Project
3.8.3 Institutional Process
3.8.4 The Khyber VMP
3.9 Resource Conservation Plans
3.10 Village Conservation Funds
3.11 Infrastructure Support
3.12 Ecotourism
3.13 Species Management and Trophy Hunting
3.14 Plants of Potential Economic Importance
3.15 Monitoring and Evaluation
3.16 Biodiversity Trust Fund
3.17 Exchange Programme
3.18 Training
3.19 Publicity and Education
3.20 Forward Plans for Remaining Period
4. PROJECT EVALUATION
4.1 Project Management
4.2 Backstopping
4.2.1 UNDP
4.2.2 IUCN
4.2.3 Government
4.3 Comparison of NWFP and NAs Field Operations
4.4 Relevance
4.5 Efficiency
4.6 Effectiveness
4.7 Sustainability
4.8 Stakeholder participation
4.9 Capacity Building
4.10 Addressing of Root Causes
5. Women in Development
5.1 Background
5.2 Findings from Field Visits During the Evaluation Mission
5.3 Constraints
5.4 Opportunities
5.5 The Need for Integrating Gender Issues
5.5.1 At Project Level
5.5.2 At Community Level
6. Project Impacts and Contributions
6.1 Impacts at Community level
6.2 Contribution to national efforts to conserve biodiversity
6.3 Global Benefits and Contributions
6.3.1 Contribution to the larger context of GEF
6.3.2 Contribution to Commitments under the Convention on Biodiversity
6.3.3 Application of Incremental Cost Principle
6.3.4 Sharing of lessons
6.3.5 Leveraging of Additional Resources
7. SUMMARY OF FINDINGS
PART ii
LOOKING TO THE FUTURE
8. INTRODUCTION
9. GOVERNMENT STRATEGY
10. GOP/WORLD BANK GEF PROPOSAL
10.1 Background
10.2 Issues
10.3 Options
11. RECOMMENDED STRATEGY AND APPROACH
11.1 Geographical Coverage
11.2 Global/GEF significance
11.3 Title
11.4 Duration
11.5 Project Identity
11.6 Objective
11.7 Implementation Arrangements
11.8 Core Outputs and Activities
11.9 Biodiversity Trust Fund
11.10 Plants of Economic Importance
11.11 Capacity Building
11.12 Budget Requirements
11.13 Incremental Costs
11.13.1 General
11.13.2 System Boundary
11.13.3 Baseline
11.13.4 Domestic Benefits
11.14 Co-financing
11.15 Other Design Issues
12. PROJECT PREPARATION
13. CONCLUSION
ATTACHMENTS
ABBREVIATIONS AND ACRONYMS
|
AIB |
Activity Initiation Brief |
|
AKRSP |
Aga Khan Rural Support Programme |
|
BDCC |
Biodiversity Coordination Committee |
|
EAUD |
Environment and Urban Affairs Department |
|
GEF |
Global Environment Facility |
|
GOP |
Government of Pakistan |
|
IUCN |
IUCN - The World Conservation Union, Pakistan |
|
NAs |
Northern Areas |
|
NRM |
Natural Resource Management |
|
NCS |
National Conservation Strategy |
|
NGO |
Non-government organisation |
|
NWFP |
North West Frontier Province |
|
PC-II |
GOP Planning Committee project document |
|
PFI |
Pakistan Forest Institute |
|
PMC |
Project Management Committee |
|
PRIF |
GEF Pre-Investment Feasibility Fund |
|
TOP |
Terms of Partnership |
|
TPR |
Tri-Partite Review |
|
UNDP |
United Nations Development Programme |
|
VCF |
Village Conservation Fund |
|
VMP |
Village Management Plan |
|
VO |
Village Organisation |
|
VWG |
Village Wildlife Guide |
|
WID |
Women in Development |
|
WO |
Women’s Organisation |
EXECUTIVE SUMMARY
Project Evaluation
Introduction:
The project "Maintaining Biodiversity in Pakistan with Rural Community Development" commenced at the beginning of 1995, operating in the Northern Areas and the North West Frontier Province of Pakistan, a very large mountainous regio n which is the meeting point of the Himalaya, Hindu Kush and Karakoram. This mid-term evaluation and formulation mission occurred in April 1997. The following is a summary of the findings and conclusions of the evaluation team:
Coverage:
Valleys so far included in the project have a total area of approximately 570,000 hectares, and contain representatives of all the ecosystem types of the northern mountains.
Process:
The project has adopted a sound process leading from initial identification and selection of participating valleys, through a Participatory Rural Appraisal process to preparation of Village Management Plans. The process has achieved a strong sense of ownership by the communities of the process and the resulting plans. Some plans display a particularly strong sense that they are prepared by the communities and that they genuinely reflect their needs. Through the management plans, mos t of the communities demonstrate an awareness in their own context of concepts such as biodiversity, conservation and sustainable use.
The project has completed five resource conservation plans. Overall, they are of a high standard and provide a good basis for further development. This project, like similar community based initiatives elsewhere, uses wildlife use as a vehicle for achieving a much broader ecosystem conservation goal. This approach is sound and, in the case of the mountains of Pakistan, essential if there is to be any serious attempt at biodiversity conservation.
Village Conservation Funds:
Village conservation funds are an innovative approach to developing commitments and involving communities in the management of conservation funds. They are showing great promise.
Infrastructure Support:
Coming out of the VMPs and formalised in TOPs is the infrastructure support component of the project. To date, this has mostly assisted with the construction of irrigation channels which serve to increase productivity of lower areas , thus decreasing pressure on the high altitude grazing lands.
The development of ecotourism is still in its infancy. It was clear to the mission that this should be a priority for the future.
Medicinal Plants:
This component of the PRIF project has not been entirely satisfactory to date, primarily because the base documents gave only cursory and somewhat vague direction as to what was intended. The team believes, within this project and i ts successor, plants of economic importance should be treated only as an existing or potential economic and social resource for the communities involved. A broader programme for identification of plants of potential economic importance, perhaps on a natio nal basis, may well be valid as a separate exercise. However, the team believes that it creates confusion to graft such a broader programme on to the community-based project.
Monitoring and Evaluation:
A comprehensive programme has been developed by IUCN for monitoring. As this programme is new, its effectiveness is yet to be determined. It is important to realise that there are two separate M&E activities. The project must mo nitor and evaluate itself, but longer term process monitoring is also critical.
National Biodiversity Fund:
The team believes that it will be important to keep the action towards the national fund distinct from the project’s core activities. A regionally-based fund could provide a vehicle by which donor funds might be sought and channeled through the VCFs to support community-level activities.
Comparison of Northern Areas and NWFP Programmes:
The team was able to compare the operation in the NAs implemented by IUCN and that in NWFP implemented by the NWFP government. Both operations are very impressive in the success that they are achieving, and both measure up well agai nst similar operations elsewhere in the world. The two operations are somewhat different in nature, but both management systems have strengths and are demonstrating the potential for continued and growing success.
General Evaluation:
Summary of Evaluation:
In the team’s opinion, the PRIF project is fulfilling its purpose admirably. It has certainly proved the efficacy of a community-based approach to biodiversity conservation and sustainable use in the mountain areas of northern Pakis tan. It provides a very good foundation for the launching of a full-scale project. Given that the project is still only part way through the PRIF phase, and considering the great difficulties imposed by remoteness and logistics, the progress has been exce llent.
FUTURE OF THE PROJECT
Introduction
The team strongly recommends that an on-going operational project is approved and launched on schedule. In planning the future project and its relationship to other projects, it is necessary to respect the GOP’s "commitment to a hol istic approach to conserving biodiversity so that no single initiative by any one of the implementing agencies compromises the opportunity to obtain funds for other initiatives." The team suggests the need for the several proposed GEF project proposals to proceed in parallel, and/or the need to make some adjustments to the GOP/World Bank/GEF Protected Areas proposal to strengthen that proposal and to remove the potential for conflict and overlap with operational phase of the proposal under evaluation.
Outline of Proposed Operational Project
In summary, the team’s proposals for the next phase are:
Conclusion
The team recommends strongly that the roll-over to the full scale operational phase should proceed as planned. To do otherwise would lead to a major loss of credibility and a sense of disappointment among the affected communities. I t would also compromise a very promising opportunity to conserve the globally significant ecosystems and species of the mountains of Pakistan.
PART I:
PROJECT EVALUATION
Background and Purpose of mission
The project "Maintaining Biodiversity in Pakistan with Rural Community Development" (PAK/93/G41) was approved in June 1994 under the Global Environment Facility Pre-Investment Fund (PRIF) with a budget of US$ 2.5 million. (For the p urposes of this report, it will be referred to as the "PRIF project" or "the project"). The project was a response to concern that natural habitats in the northern mountains of Pakistan were deteriorating and that populations of threatened wildlife specie s were declining. There were no incentives for rural people to maintain or manage renewable natural resources sustainably. Protected areas had been designated and threatened species had been identified and listed for strict protection under national and p rovincial laws, yet populations of key species continued to decline. It was suggested that, for sustainable development to succeed, while maintaining and enhancing Pakistan’s biodiversity, rural people would have to be considered. It was decided that an a lternative approach is needed that involves rural people in the solution rather than considering them as the cause.
The PRIF project commenced at the beginning of 1995, operating in the Northern Areas (NAs) and the North West Frontier Province (NWFP). In September 1996, a Tripartite Review Meeting (TPR) agreed on the need to undertake, as soon as pos sible, a mid-term evaluation which would also provide the foundation for the formulation of a full scale project for GEF funding. The meeting also recognised the importance of the mission as a basis for coordination with the development by the World Bank of a Protected Areas Management project proposal for GEF funding.
The evaluation/formulation mission was scheduled for November-December 1996, but it proved impossible to field the mission in time to avoid the onset of the northern winter. It was rescheduled to April 1997.
The evaluation/formulation team comprised Keith Garratt, an independent conservation/environment consultant with GEF experience who is based in New Zealand (Team Leader), Michael Murphree, Executive Officer of the Southern Africa Su stainable Use Group based in Zimbabwe, and Kalimullah Shirazi, Deputy Secretary (Land and Water), Ministry of Environment, Local Government and Rural Development, Islamabad. The team was assisted by Kent Jingfors, Biodiversity Advisor to the project, who is based in Gilgit. During its inspections, the team was accompanied by various project staff and by UNDP staff. Shafqat Hussein, the Project Administrator, accompanied the team throughout the inspections, with the difficult task of organising the complic ated logistics.
In retrospect, it is apparent that the team should have included a woman with experience in gender issues. It was not possible for an all-male team to make a meaningful assessment of gender issues and implications. The cultural norms of the area meant that it was not possible for the male team to seek direct communication with women at the grassroots level in the villages. With one or two exceptions, women were notable by their absence at consultation meetings at village level, and in s ome villages were completely invisible. In the NAs, the team was fortunate to be accompanied by the project WID advisor, Siobhan Warrington, and Razina Bilgrami, UNDP Programme Officer. In some villages, they were able to meet directly with the women and to transmit concerns and issues to the team. Nevertheless, gender is an important topic which the team was not able to give the attention that it deserves.
Prior to the commencement of the field mission in Pakistan, the Team Leader had consultations with relevant staff of UNDP in New York and the World Bank in Washington DC.
Following initial familiarisation and meetings in Islamabad on the 7 and 8 April, the team spent the period from 9 to 16 April traveling in the project area. During this time, the team was able to visit and meet with several of the comm unities that are included in the project. It also had the opportunity to meet with project staff and key personnel in various government and non-government agencies. Details of the field itinerary are given in Attachment 1, and a list of key people who we re met is provided in Attachment 2.
In addition to providing very valuable insights into the conduct and achievements of the project, the field inspections confirmed for the international members of the team the unique nature of this northern mountain area of Pakistan. It is a remarkably spectacular and rugged area. As the meeting point of three of the world’s great mountain ranges, the Himalaya, Karakoram and Hindu Kush, it is immediately apparent that it is an area with natural values of international significance.
The field inspection also gave the team some appreciation of the major practical and logistical difficulties of implementing a project such as this in this extremely rugged and remote area. For example, the first item on the travel itin erary was to fly to Gilgit, leaving Islamabad at 5-30am on 9 April, with a full day of activities scheduled to occur that day following arrival in Gilgit. In practice, the flight was forced to turn back part way to Gilgit because of bad weather. The team eventually left Islamabad by vehicle at 9am, and arrived in Gilgit at midnight. This necessitated some amendments and reduction of the inspection programme in the Northern Areas.
The team was scheduled to leave Skardu for Islamabad by air on the morning of 14 April to commence its inspection programme in the NWFP. This flight was canceled, necessitating a 12 hour drive to Besham to link with NWFP programme staff for an amended programme. In practice, rain caused blockages on the Karakoram Highway, and the team was forced to shelter for the night at Dassu, some three hours short of Besham. This created a further half day delay and further drastic contraction of t he planned inspection schedule in the NWFP. The team was not able to visit the Chitral area where the programme in NWFP has been most active and is most advanced.
A further indication of the logistical difficulties of working in this terrain is that in the course of the one week of the field inspection, the team spent approximately 60 hours in vehicle travel. In retrospect, it is apparent the tea m would have been more likely to be able to complete its field inspections had the mission been scheduled perhaps 1 or 2 months later, or as originally scheduled in November 1996.
The period following the field inspections was occupied with further consultations in Islamabad, preparation of a draft report, consultations with key agencies on the draft, and the completion of this final report.
The project title "Maintaining Biodiversity in Pakistan with Rural Community Development" succinctly expresses the objective of the PRIF project. In the UNDP Activity Initiation Brief (AIB) for the project the development objectives are given as:
Operational objectives are given as:
Two further potentially major project functions described in the AIB and the PC-II document are preparatory work for a national Biodiversity Trust Fund and research into plants of economic significance.
The Ministry of Local Government and Rural Development (Biodiversity Unit) is the Executing Agency for the PRIF project. IUCN/Pakistan is the Implementing Agency. A Biodiversity Coordination Committee was to facilitate inter-agency communications and coordination at the national level in the area of biodiversity conservation. In practice, a Biodiversity Working Group has been formed, but has had little role in this project. The Project Management Committee (PMC) provides policy guid ance for the management of the project.
IUCN provides overall project management and technical support and funds are routed to the field level through IUCN. At the field level, IUCN implements the project in the Northern Areas from an office in Gilgit and a sub-office in Skar du, with 8 technical/professional staff. In the NWFP, the project is implemented in the field by a Biodiversity Project Unit within the Forest and Wildlife Department of the Government of NWFP, under the direction of a Project Coordinator based in Peshawa r. There are 9 technical/professional staff and Range Officers.
District Conservation Committees have been established in four districts - Gilgit, Skardu and Ganche in the NAs, and Chitral in NWFP. Members include the Deputy Commissioner as Chair, the Assistant Commissioner, the Deputy Superintenden t of Police, the Divisional Forest Officer, community representatives, an AKRSP representative and an IUCN representative.
The outputs and actions that were proposed for the project are outlined in detail in the AIB and the PC-II, and need not be repeated here. They were summarised in the AIB as:
Provision was included for the evaluation of wild plants of potential economic value through arrangements with the Pakistan Forest Institute (PFI) and the HEJ Institute at the University of Karachi.
An activity to research the requirements for a national Biodiversity Trust Fund was included. Public awareness and communication activities were proposed, and a Special Studies Fund to support applied research was to be established.
A discussion of the actual activities and achievements to date is given in 3 below. The PC-II noted that the project would follow a "process" approach rather than a "blueprint" approach, and would be a learning process. The project desc ription, targets and budgetary estimates were recognised to be of an indicative nature. Consistent with this approach, the team has given limited attention to checking that listed outputs have been achieved. It has concentrated more on identifying actual achievements and on assessing their inherent relevance and value in meeting basic project objectives and the needs of the biodiversity and people of the project area.
Contribution to Policy and Legislation Development
As previously mentioned, one of the operational objectives of this project was to "advise" government on the necessary policy and legislation required to support this type of initiative. One of the key assumptions is a commitment by government to provide an enabling environment that gives rural communities the necessary incentives to use and manage natural resources wisely. This generally requires the development of supportive policy and legislation (especially true in countries wit h a colonial history where legislation tends to be restrictive). In Pakistan, British colonial rule had established restrictive legislation that became largely ignored by rural communities with the advent of independence. Despite a revision of the legisla tion in 1968, the legislation continued to be "top down" with continuing negative effects on wildlife populations - " the centralised power and top down approach deprived rural communities of their traditional user rights, their sense of ownership of the wildlife resource, and any incentives to actively participate in the conservation of wildlife and wildlife habitats.".
This PRIF project has been involved in the development of a draft policy for wildlife in Pakistan that moves towards establishing a framework for legislative reform. The draft policy provides a set of guiding principles that empower and assist rural communities with the management incentives needed to ensure sustainable wildlife use. The team accepts that this is a draft policy within the context of a wider national debate on policy and legislative reform. The team also notes the need f or developments and experience from this project to feed into district, provincial and national conservation strategies, which can in turn become part of the supporting environment for pursuing project objectives. The team has noted that a comprehensive N ational Conservation Strategy already exists, and that provisions in that are fully consistent with the project objectives. We are also aware that provincial and district strategies are in various stages of preparation and completion.
Furthermore, a Biodiversity Action Plan is also being developed for the GOP by IUCN as a component of the preparation process for the GOP/World Bank Biodiversity Action Plan/Protected Areas Management Project proposed for GEF funding. T his will also presumably be of relevance to community-based biodiversity management. However, the team has not seen a draft of the BAP.
Identification of Project Valleys
The selection of project sites or valleys for the PRIF phase of this project was based on a combination of ecological and social factors. For the most part, the project has wisely selected areas that have complementary programmes al ready working in the community. This has resulted in the highly successful relationship between this project and the AKRSP. In NWFP, the selection of valleys differs slightly from the Northern Areas. However, for the most part the selection is consistent and in the valleys visited by the mission was warranted in all cases. The project has developed a tabular valley assessment form that is a very clear indication of the criteria used in selecting each valley. The following sketch map shows the approximate location of the current project sites.
The mission was told that in the Ramboor Valley a conflict between three communities has resulted in a suspension of project activities. The project staff are awaiting the resolution of the conflict before proceeding with further projec t activities.
In light of the above the mission recommends that:
While it may be useful to develop a ranking of priority areas for project activities, the project should be "demand driven" and contain enough flexibility to respond to communities that may fall outside the set priorities or criteria. The mission has noted and commented that the presence of AKRSP has been a very positive factor in the success of this project through its establishment of village organisations. While the mission recognises this advantage, it would equally be concerned to see this as a limiting factor.
Rapid Assessments of Biodiversity
The project in its valley selection criteria and through the development of the village management plans has been able to complete rapid assessments of the status of biodiversity in most of the project areas. The project has been wo rking with the villages using PRA techniques and has trained locally selected village wildlife guides for census work. The extent of field data collected by the project must be viewed in the light of the extreme physical conditions of the area where altit udes of 20,000 feet are common. The approach of the project is therefore primarily to concentrate on identifying and monitoring ecosystems. In light of the field trip, the mission is satisfied that this approach is appropriate for this type of project and the PRIF phase. Using this method, the project currently covers representatives of ecosystems and species noted for their "global significance to biodiversity".
The total number of project areas, villages and rural people involved in the PRIF project, as well as the total area declared as Community Conservation Areas (CCAs), is given below. A more detailed summary is provided in Attachment 3.
Region |
No. of Project Areas |
No. of Villages |
No. of House-holds |
No. of People |
Size of CCAs (hectares) |
Northern Areas |
6 |
18 |
1,814 |
17,740 |
256,000 |
NWFP |
6 |
28 |
2,970 |
27,350 |
313,750 |
Total |
12 |
46 |
4,784 |
45,090 |
569,750 |
The project areas lie within the mountainous Himalayan and Pamir-Karakoram biogeographical provinces. Major vegetative zones based on Roberts (1991) include:
The representation of the vegetative zones in the initial project areas in NWFP and Northern Areas is estimated based on the small-scale map provided by Roberts as follows. Note that all areas are expressed in km2:
|
Vegetative zonePSCD |
N/A |
0 |
265 |
265 |
N/A |
||
|
DACD |
28,138 |
0 |
1,130 |
1,130 |
4.0 |
||
|
ASMA |
11,255 |
1,125 |
815 |
1,940 |
17.2 |
||
|
HDC |
43,412 |
700 |
874 |
1,574 |
3.6 |
||
|
HMTF |
13,667 |
350 |
0 |
350 |
2.6 |
||
|
STPF |
7,235 |
100 |
0 |
100 |
1.4 |
||
|
STDMDF |
3,216 |
100 |
0 |
100 |
3.1 |
||
Thus, the Alpine scrub and moist alpine zone is well represented (17.2%) in the project areas followed by the Dry alpine and cold desert zone (4.0%) and the Himalayan dry coniferous zone (3.6%).
Of the 13 threatened mammal species in Pakistan (1996 IUCN Red List), 4 are known to occur in one or more of the project areas: markhor, snow leopard, Ladakh urial and Asiatic black bear. The endemic and endangered woolly flying squ irrel has also been confirmed to occur less than 10 km from one of the project sites in Northern Areas (Astore Valley). Other mammals designated as "near threatened" that may occur in the project areas include Himalayan musk deer (confirmed), blue sheep ( possible), grey goral and long-tailed marmot (confirmed). The brown bear is also known to occur in project areas adjacent to the Deosai Plains (e.g. Kachura). The status of these species as follows:
Wildlife Species |
Status (IUCN, 1996) |
Markhor (Capra falconeri falconeri) |
Endangered |
Snow leopard (Uncia uncia) |
Endangered |
Ladakh urial (Ovis vignei) |
Endangered |
Asiatic black bear (Ursus thibetanus) |
Vulnerable |
Woolly flying squirrel (Eupetaurus cinereus) |
Endangered |
Musk deer (Moschus chrysogaster leucogaster) |
Near threatened |
Blue sheep (Pseudois nayaur) |
Near threatened |
Grey goral (Naemorhedus goral) |
Near threatened |
Long-tailed marmot (Marmota caudata) |
Near threatened |
Brown bear (Ursus arctos isabellinus) |
Not listed |
In addition to mammals, a number of bird species at risk may occur in one or more project areas based on range maps provided by Roberts (1991). These include Pallid Harrier (near threatened), Sociable Lapwing (vulnerable), Long-billed B ush-warbler (vulnerable), and white-throated tit (near threatened).
Initially, the focus of the project has been on preparing species-specific wildlife conservation plans (e.g. ibex) that provide communities with the ability to monitor, sustainably use and protect the species and its habitats. The prima ry habitats of ibex are the high pastures that are now also used for livestock grazing and fuelwood collection. The success of future conservation efforts will largely depend on whether rural communities will have sufficient reasons or incentives to maint ain populations of wildlife in preference to their domestic livestock. By demonstrating the potential economic value of ibex through a limited and strictly enforced community-based trophy hunting program, where the financial benefits can be used to sustai n local conservation efforts, communities will be provided with a powerful conservation tool. Conservation efforts directed at ibex and its high elevation habitats will also benefit a range of other species, including snow leopard.
Participatory Rural Appraisals (PRA)
A major component of establishing a relationship with target villages is the use of PRA. The use of PRA can in the initial stages be highly beneficial to establishing a relationship with a community. The techniques currently employe d by PRA have evolved from several applied social science techniques developed during the 1970s and 1980s. However, it is important to realise the limitations of PRA, in that it is only a tool that assists in building relationships with communities, provi ding the framework necessary to develop a greater understanding of the mechanics of a particular community and therefore establishing the basis for developing plans and activities.
Ultimately, PRA cannot substitute for a good working relationship between the project staff and the community. The success of the project in these communities will depend on the level and type of interaction occurring between field staf f and the community. PRA can assist in structuring this and is very useful for self examination by communities. Beyond this, the project staff will need to rely on experience over time in determining the scope of their interactions with the communities. T his point was brought out during the team’s interview with Mr. Khaleel Tetlay, Regional Programme Manager of AKRSP in Skardu, when he referred to three techniques - RRA (Rapid Rural Appraisal), PRA and TRA (Tetlay Rural Appraisal). The point being made wa s that successful project implementation is a combination of techniques determined ultimately by the ability of the field staff to interact and understand the dynamics of each community.
The PRIF project has so far held several PRA workshops with target villages. It is evident that the use of the PRA technique has been of considerable benefit in the following ways:
The PRA technique has clearly shown its usefulness as a tool for both project staff and communities. In discussions in the field, it appears that project staff are comfortable with the methodology. From observations in the Kachura commu nity, it is a tool that is effective in stimulating community participation. It is therefore important to note that in the reports produced by the project staff, very little is said about the PRA process (reportedly there have been two evaluations of PRAs held with women in the project). This is an area that needs to be addressed. The following points should be noted regarding PRA and this project:
Considering the above, it is recommended that when moving into the next phase of the project the following are considered:
The primary lesson learned during the PRIF project regarding PRA is that the social science skills required for successful project implementation will need to be strengthened. This will be particularly important in the context of a cont inuing programme with an expanded scope and additional communities. It was also noted by the team that the sociologist recruited by the NWFP was no longer in place. This needs to be reviewed and appropriate corrective measures taken by the implementing pa rtners.
The key to this project is the development of the Village Management Plans (VMP), where these plans achieve three things:
The VMP for Khyber Village in the Northern Areas is an outstanding document, written by the community. It clearly states the problems being faced by the community, the attempts to date by the community to address the problems, community perceptions of the solutions to the problems and their vision for the future. While project staff facilitated the process, this plan was written by the community and is printed in the simple, colourful language of the people of Khyber. The validity of th is document was impressed upon the mission during our meeting with the community in Khyber. It is encouraging to see a plan of this nature in an era of technical reports and complex (often external) planning.
Not all of the VMPs developed in this project show the same extent of community drafting as shown in the Khyber case. The VMP for the Arkari Valley in NWFP contains an extensive analysis of the Akari community, economic activities and t he status of its natural resources. However, the plan falls short of the clear and simple definition of problems and solutions exhibited in the Khyber plan. It is not the intention of this report to provide a critical analysis of each VMP. However, both c ommunities used a PRA approach but with different results. Such differences should be picked up by the project M&E system and evaluated as such. Experience elsewhere has shown that there will be situational differences in these programmes and that the se differences allow communities to develop a sense of ownership for their own programme. Equally though, it is important to monitor and evaluate these differences. This aspect will need greater attention by the project in the future.
The Development of VMPs In The Project
The VMPs are developed in an interactive process using PRA techniques, with a resulting strong sense of proprietorship by the community for the plan. The process for developing the VMPs was broadly outlined to the mission as follows :
The result is a plan that has been developed through an interactive "grassroots" approach, undergone a wide review process and enjoys the support of all concerned parties. The danger in this process is as follows:
The use of techniques such as PRA for the collection of data and information about communities is important. The application of these techniques (and the information gathered) to the planning process must be done with caution. The infor mation contained in the Arkari Plan is important field data and is critical for the implementation of the project. It however, is less critical as the information or inputs required for a community’s own VMP.
The difficulty faced by the project staff is one of divergent perspectives. The project staff work and plan within the hierarchical system of their own institutions, with a set of questions and objectives that are unlikely to be the sam e as those of the community. The challenge of this project is to enable the type of planning done by the Khyber community, the importance of which was noted by Mr. Khaleel Tetlay of AKRSP. The application of the Khyber VMP shows the extent to which the co mmunities view the management of their wild and domestic resources as integral to their community development.
The diagram on the following page shows the institutional process used in developing VMPs in the project areas.
The Khyber community have lived and survived off the resources of their valley for hundreds of years. This community, without the formal terminology, is acutely aware in their own context of concepts such as biodiversity, conservati on and sustainable use. Furthermore, they clearly express this in their VMP:
"The valley is now left with inadequate natural forests. Consequently wildlife habitat and ecological needs demand our attention. In case this need is not met or we do not adopt any appropriate strategy for the use of wild forest the n in the next few years the valley will be deprived of forest and wild plants. As a result it would be difficult to live in the place."
The recognition in the last sentence of the linkage between survival and the sustainable use of natural resources shows the high level of understanding that the people of Khyber have regarding the linkage between themselves and the envi ronment. This community views the management of its resources from an ecosystem level. They realise that by improving lowland pasture they can improve the status of higher grazing utilised by wildlife. This community views this project as a part of its fu ture survival and correspondingly express a high degree of proprietorship over it.
With the intent of providing strategies for the conservation and management of specific species, the project has completed five resource management plans. The plans provide the basis for resource use (through limited trophy hunting) and protection of resources through the designation by local government of Community Conservation Areas. The plans produced so far are:
These plans differ significantly from the VMPs as plans with a high degree of technical content that is developed by the project staff in consultation with the communities. This is not necessarily negative as the audience for these plan s is largely external. As mentioned previously, these communities tend to place great emphasis on management at the ecosystem level. These species plans are very important and will play a significant role in assisting the communities to realise the benefi ts from their natural resources through activities such as trophy hunting. As community capacity increases, so the level of community control in the drafting of these plans should increase. Observing discussions with the Hushey community, it was clear tha t while these plans tend to be technical, they attract considerable discussion and the communities certainly identify with them. Some of the sanctions developed by the communities and incorporated into the plans show the differing methods of local control . As an example, the Ibex Conservation Plan for the Arkari Valley states:
"No body [sic] from the valley will attend the marriage ceremony and funeral of the accused till he pays the required sum to the cluster [the cluster is a group of 11 villages in the Arkari Valley] and apologises before the cluster."
Local project staff report that this sanction has eliminated all local "poaching".
Overall the RCPs developed by the project are of a high standard and are certainly the basis for further development. Commendable points include:
Specific recommendations for the RCPs include:
The village conservation fund is an innovative approach to developing commitments and involving communities in the management of conservation funds. The operation of these funds is outlined in the diagram below:
It is encouraging to see this project testing new ideas such as the VCF. As a result this project has been able to:
VCFs have now been established in 5 communities in NWFP and NAs, representing an initial investment by these communities of Rs 351 000 or US$ 8775.
Coming out of the VMP and formalised in a TOP is the infrastructure support component of the project. Once again, the implementing agencies have taken the sound approach of working with and letting the communities determine their ow n priorities. In most cases, the communities have opted for an irrigation canal. This is a central component to resource management, as these communities lie mostly in arid areas. The rationale employed by the communities and supported by the project staf f is that by improving the lower pastures through irrigation, the high pastures can be retained for wildlife. Furthermore, the irrigation canals serve as boundary lines between livestock and agricultural areas and wild areas. The mission saw several of th ese irrigation canals that are being built by the communities and was impressed by the skill being employed to divert water, often several kilometres along very steep slopes.
There are seven water canal projects which including the contribution of the local communities, have cost a total of Rs 5,067,070or US$ 126,676.
Globally there is considerable debate over the term "ecotourism" and what constitutes eco-friendly tourism. In the context of this project, ecotourism refers to low volume tourism, primarily comprising people wishing to hike on the lower level mountain trails. The potential for this type of tourism varies between the different communities. In some communities such as Hushey, the potential is high, especially if the community is able to tap in to the major climbing expeditions that p ass through Hushey on their way to the high mountains of Masherbrum, Gasherbrum and K2. Other communities can also offer tourists cultural experiences along with scenic trails. Given the other priorities of this PRIF phase, the development of ecotourism i s still in its infancy. However, it was clear to the mission that this should be a priority for both communities and project staff in the future.
Species Management and Trophy Hunting
The success of any community-based initiative is determined ultimately by the extent to which communities are in a position to make their own decisions regarding species management. The success of community based programmes and the achievement of sound resource management can be assessed by the extent to which a few guiding principles are applied. Five key principles relating to rural communities and the management of natural resources that have been found to apply in initiatives of this nature elsewhere, and that are relevant to the projects in Northern Areas/NWFP, are:
Within the context of the PRIF, this project could not be expected to have addressed all of the above. However, by using these principles as a reference, it is possible to see the direction and extent of achievements during the PRIF. Ov erall this project has done exceptionally well. This project, like similar community based initiatives elsewhere, uses wildlife use as a vehicle for achieving a much broader ecosystem conservation goal. This approach is sound and, in the case of the mount ains of Pakistan, essential if there is to be any serious attempt at biodiversity conservation.
Trophy hunting is one management option. If correctly managed, it has a very low environmental impact. A cost benefit analysis of trophy hunting shows that for the level of input the returns from this form of use are very high. This ret urn in a system managed by local communities results in improved species and habitat management.
Trophy hunting is not the only form of wildlife use that can be employed by rural communities. Other management options include photographic tours, live animal sales and cropping. The critical issue is the extent to which national and i nternational policies on species use are reflective of local situations, needs and interests. Certain options acceptable in one situation may be inappropriate in others.
In discussions with several communities and with project staff, it was clear that a careful and cautious approach is being taken on the issue of wildlife use. The main points from this are:
The recommendations following from this are:
Plants of Potential Economic Importance
This component of the PRIF project has not been entirely satisfactory to date. The team understands that it was originally proposed that this matter would be the subject of a broader stand-alone project, but that a decision was made to link it with the PRIF project. It appears that the graft has not been entirely successful, and that this is an area of the project that has created difficulties. The project recently commissioned a comprehensive report on this issue, and the draft rep ort has been very helpful to the team in considering this issue.
IUCN as the project implementing agency entered into Memoranda of Understanding with the Pakistan Forest Institute and the HEJ Research Institute of Chemistry to undertake activities related to this component of the project. The r ecent draft report referred to above provides detailed comments on the actions taken under each of the items of the MOUs. While some progress has been made, it is apparent that there has been a considerable degree of confusion and lack of clarity regardin g the intent and purpose of this component of the PRIF project. The team believes that this is due not to any deficiency on the part of IUCN as implementing agency or of other agencies involved, but rather because the AIB and PC-II documents gave only cur sory and somewhat vague direction as to what was intended.
A problem is that the subject of plants of potential economic importance can cover a very wide range of activities. At one extreme, it may entail no more than helping local communities to ensure continued access to plants of traditional importance to them, for example by helping them to identify and implement a sustainable harvesting level from their surrounding environment. At the other extreme is the establishment of a systematic national biodiversity prospecting and research programm e to identify, develop and market new products from the components of biodiversity. Costa Rica provides an example where this has become a multi-million dollar national activity.
The problem with the PRIF project component is that it is not clear where it lies along the spectrum between these two extremes. In particular, it seems unclear whether it was intended that the activities under this component would be r elated to the valleys selected for participation in the community-based planning and management programme, or to some broader geographical area.
The team is clear in its view that, within the scope of the PRIF project and its successor operational phase, plants of economic importance should be treated only in their role as an existing or potential local economic and social resou rce for the specific communities involved in the programme. In this respect, they should be considered in the same way that ecotourism or trophy hunting potentials are considered where they exist in the valleys that are part of the programme. In other wor ds, within this project plants of potential economic importance should be considered only to the extent that they relate directly to fulfilling the objectives of the project as quoted in 2.1.
A broader programme for identification of plants of potential economic importance, perhaps on a national basis, may well be valid as a separate exercise. However, the team believes that it creates confusion to graft such a broader progr amme on to the community-based project.
The PRIF phase of this project has had four external evaluations including this mission (Dr. Steve Edwards has produced four "Mission Reports" as a component of project monitoring) and has now benefited from the establishment of a m onitoring system through the Karachi office of IUCN. Monitoring and evaluation is central to the success of this project. The application of an adaptive management approach requires that there is a continual process of "experimentation" and review. Failur e to establish a good monitoring system will impair the ability of the project and communities to develop management practices based on learned experience.
A comprehensive programme has been developed by IUCN for monitoring and evaluation, and one person (Mr. Shafqat Hussain) has been assigned the responsibility of implementing this programme. As this programme is new, its effectiveness is yet to be determined. The mission was presented with all current documentation (including the Edwards reports) and is satisfied with the approach being taken. In light of this, the following points are made:
As noted earlier, the AIB and PC-II documents provide that, during the PRIF phase of the project, "the requirement for establishing a National Biodiversity Trust Fund will be researched". Some very useful initial work on this has be en done under contract by IUCN Pakistan in Karachi. A report into the legal issues involved in establishing a trust fund in Pakistan has been prepared. Representatives of IUCN and UNDP attended the Asia-Pacific Forum on National Environment Fun ds held in Cebu, Philippines in February 1997, and provided a useful report which discusses the issues to be considered in establishing a national fund. More recently, a draft concept/options paper has been produced.
The work done to date provides a basis for further consideration and development of the proposals for a national biodiversity fund. The concept paper advances a suggested basis for a fund in Pakistan, and sets out several options for go vernance. Without more detailed knowledge and investigation, the evaluation team is not in a position to comment on the proposal and options put forward. The paper can be used as a basis for the further consultation processes that will be required before final decisions are made.
The team believes that it will be important to keep the action towards the national fund distinct from the project’s core activities. As will be outlined in more detail later, the team believes that the on-going project should be focuse d specifically on community-based biodiversity conservation and sustainable use across the northern mountain ecosystems in NWFP and the NAs. The development of a national fund does not sit comfortably within this objective.
We see a valuable role for a northern-based fund (or funds) which specifically aims to support the project objectives. The team has noted the potential effectiveness of the Village Conservation Funds that are being established with the support of the PRIF project. A regionally-based and managed fund could provide a vehicle by which donor funds might be sought and channeled through the VCFs to support appropriate activities that have been identified through the village management plannin g process and the species and biodiversity conservation plans. This concept is discussed more fully in 11.9.
During October-November 1996, a visit by project staff to Eastern and Southern Africa was undertaken. Following this a report of the tour was prepared by Amjad Virk about the tour and lessons learned. This tour was clearly beneficia l to the participants and some of the recommendations made by Mr. Virk in his report are indicative of the usefulness of this exercise. It is therefore recommended that:
Following extensive discussions during the field visit, the mission noted that the following had been covered under training:
It is recommended in light of the above that this project should:
With the assistance of the Communication Unit of IUCN Pakistan in Karachi, the project has produced some useful publicity material. This includes a poster, a brochure and a newsletter. These are all useful in raising public awarenes s of the project and its objectives. The team is not aware of the manner in which these are disseminated. This is of course an important issue, as publicity material is not effective until it reaches an appropriate audience.
An interesting and impressive feature is a video film of project activities produced entirely within the resources of the Gilgit project office, with a project driver as the primary camera operator. This is of remarkably good quality co nsidering the limitations.
For the future, a continued publicity component is important. During the PRIF preparatory phase, there has understandably been little effort to publicise the achievements more widely. The PMC has urged that more publicity material shoul d be prepared. The team believes that the project is developing some important experiences that should be spread much more widely, including in the international arena.
For the next phase, careful thought must be given to supporting capacity building through formal and informal education at all levels within the project area.
Forward Plans for Remaining Period
The PRIF project is scheduled to terminate towards the end of this year. However, the team was told that the efficient use of funds to date will allow the project to continue for up to one more year beyond that time. In the NAs, IUC N has plans to extend the project coverage to include two areas in the Diamer district, the Mushkin-Dushkin-Doyan area and the Bunji area, and the team observed good progress in the new Kachura project area. A feature of the up-coming project areas is tha t they will involve several communities working in collaboration across broader areas, allowing for more continuity of ecosystem management.
In the NWFP, the project is in the first stages of consultation with villages in the Swat valley. The team observed some of the early consultation during a visit to Buner village, and the prospects appear promising. The Buner proposal p rovides an interesting contrast to other project areas, in that the community is comparatively less impoverished. This means that in this area there will be comparatively less initial emphasis on community development.
From our limited observations, the team has no criticism of these forward plans for the remainder of the PRIF project. Probably the main issue to be resolved is the degree to which project resources should be directed over the remaining period "to work out the scope and modalities of the full scale project", which is a stated objective of the PRIF project as set out in the AIB. This issue is discussed further in 12.
It was not the role of this mission to conduct a detailed review of project management, for example in the form of a financial audit. The programme arranged for the team did not permit any detailed examination or analysis of project management. The following paragraphs provide some general notes on the team’s observations and findings regarding project management.
A suggestion was made to the team that project overheads are too high, and that an insufficient proportion of project funds is being applied on the ground at village level. Some enquiries were made to check whether this is a genuine mat ter for concern, but it was not possible to undertake more than a general assessment within the limitations of the mission.
In the PC-II, it was indicated that approximately US$ 12,000 would be made available during the PRIF project to each participating valley. In practice, the trend is that, in villages that have reached the stage of having an approved vil lage management plan, the amounts that are being contributed from the project are greater than this. While the funds going towards physical infrastructure at village level are quite small in percentage terms, a large proportion of the project resources go es to providing the technical and professional support and expertise that assist the villages in developing their own plans and solutions.
It appears to the team that the level of direct and indirect support to villages is consistent with the guidance provided by the AIB and PC-II. However, it was not possible within the scope and itinerary of the mission to make any detai led assessment of whether the level of overhead expenditure is appropriate. This may be a subject for UNDP to pursue through its normal management and audit processes.
The team has examined the latest budget revisions and the reasons given for them, and has questioned key project staff on these. The budget revision process seems to have been well considered, transparent and thorough, and the team find s no reason to criticise the revisions or the revision process.
There appears to be some degree of uncertainty regarding the relative roles of IUCN as overall project manager and government staff responsible for specific project implementation in the NWFP. It is a somewhat unusual situation, with an NGO in an apparently supervisory role in relation to an autonomous government agency. A careful definition and agreement on the relative roles and powers of each agency may be needed for the future.
The team was not able to observe or evaluate the role and effectiveness of the Project Management Committee (PMC).
Administrative backstopping by UNDP appears to have been satisfactory, although there was some expression of concern that UNDP staff in Islamabad do not have sufficient contact with the field operations to have a real appreciation o f the issues and difficulties faced in the implementation of the project at field level. The UNDP office in Islamabad has had limited capability to provide technical backstopping and oversight in this specialist area of activity. However, the recent appoi ntment of a Programme Officer with environmental qualifications and skills promises to bring improved capacity for technical support.
This project is administered from within the environment programme of the UNDP Islamabad office. However, aspects of the project are very relevant to the objectives and functions of the other two major programmes within UNDP, Gender and Governance. UNDP should make efforts to ensure a positive two-way flow of support and information between the project and these programmes, as the team is sure that there is much that can be learned in both directions. The GEF-funded project should not b e seen as divorced from the UNDP Country Programme, but as an integral part of it.
IUCN has been able to provide effective technical support through its Islamabad and Karachi offices and through regular monitoring visits of Dr Steven Edwards of the Sustainable Use Initiative, IUCN. The cost of these interventions has been met from project funds. It does not appear that IUCN has offered significant support or assistance from its international resources and pool of expertise. While this is not a matter for significant criticism, it may be an issue to consider in pla nning for the future. One of the perceived benefits of using major international NGOs such as IUCN as project implementing agents is that they can bring the benefits of their broader expertise and experience to projects. It may be useful for IUCN to consi der the implications and obligations of its dual role as an international conservation agency of which Pakistan is a state member, and as an employed implementing agency on behalf of UNDP.
As Executing Agency, the Ministry of Environment, Local Government and Rural Development has a responsibility for backstopping and for oversight of project management. The PMC also has a supportive and monitoring role. The team had little opportunity to assess the effectiveness of these roles.
Comparison of NWFP and NAs Field Operations
As noted in 2.2, operations at field level in the NAs are conducted by IUCN, while in the NWFP, they are conducted by a Biodiversity Project Unit within the Forest and Wildlife Department of the Government of NWFP. It was obviously a matter of considerable significance and interest for the team to observe the results achieved under the two different management regimes. Unfortunately, weather and the resulting transport delays meant that the team was unable to visit the project sites in the Chitral area where the NWFP operation is most active and advanced. However, as a result of the limited field inspections that were possible, and extensive formal and informal discussions with people involved in the NWFP sector, we believe that we can make some useful observations and comparisons.
The first observation is that both operations are very impressive in the success that they are achieving in meeting the PRIF project objectives. Both measure up well against similar operations elsewhere in the world. Both are conduc ted by dedicated, enthusiastic people with a strong commitment to success. In both cases, key people appear to have the ability and leadership style to inspire confidence in the local community people, while ensuring that the communities establish and ret ain a sense of ownership of the process and its results.
The two operations are somewhat different in nature, and both have their strengths and weaknesses. Some points of comparison are:
The team’s conclusion is that both management systems have strengths and are demonstrating the potential for continued and growing success. We believe that both should have the opportunity to carry on in the short to medium term.
We observed a tendency for competition and mutual criticism between the two systems. There appears to be a need for mechanisms and a willingness to share experiences and lessons and to draw from the strengths of both approaches.
There were suggestions from NWFP personnel that they have not received the same level of technical advice from IUCN that has been available to the IUCN-implemented field operation in the NAs. The team was not able to judge the accuracy of this claim, but it is clearly a matter that must be kept under constant scrutiny.
Over the longer term, it will be appropriate to review the strengths and experiences of the two types of project management, with the objective of devising a common approach which builds on the strengths of both.
The project and the approach that has been taken to implement it are very relevant to meeting the needs of the local communities in the north and north-west of Pakistan, and to the objectives of the GEF. This becomes particularly ap parent if the practical results and geographical coverage that have been achieved in this pilot phase are compared with what might have been achieved through applying a similar degree of effort and resources through more conventional means such as creatio n and management of formal protected areas.
From the evidence available and from its own observations and enquiries, the team is satisfied that the PRIF project provides a very appropriate approach to the issues of biodiversity conservation and sustainable use in the northern mou ntains. For example, the village management plans, biodiversity conservation plans and species conservation plans that have been produced to date provide specific evidence that the nature and approach of the project are suitable and effective. At a less t angible level, the team was impressed in all communities visited with the high level of interest, animation and enthusiasm displayed by community leaders and members. The clear impression is that the stakeholders at grassroots level see the project as rel evant to themselves and their problems. That is probably the most important measure of relevance in a project of this nature.
Efficiency is difficult to judge in the course of a brief inspection. However, the overall impression is that the project is managed efficiently. The team’s inspection programme was arranged with a high degree of efficiency within t he constraints imposed by logistics and weather. The project team demonstrated a high ability to adapt and respond to the exigencies imposed by changing circumstances.
At a practical level, vehicles and equipment appear to be used efficiently and are maintained in good condition. This is an important consideration in this environment, both for safety and efficiency.
Perhaps the best overall measure of project efficiency is that, despite the good level of achievement to date, it is estimated that the PRIF project will be able to continue for a further year beyond its scheduled termination date witho ut further budget allocation.
The PRIF project is proving to be highly effective in meeting its core objectives related to conservation and sustainable use of biodiversity in conjunction with community development. As a PRIF project, a core function is of course to test the feasibility of the approaches proposed before making a commitment to longer term operational support and funding. In relation to the core activity, the team is satisfied that this has been achieved, and that it can and should form the basis f or a longer term commitment with only comparatively minor adjustments.
A practical demonstration of the apparent effectiveness of the programme is that there have recently been two cases where villagers have voluntarily released back to the wild snow leopards that had been trapped in and around the village s. In the past, they would almost certainly have been killed because they are justifiably seen as a threat to livestock. It seems certain that this change of attitude has been a result of the activities under the PRIF project.
As outlined elsewhere, the project has been somewhat less effective in the component related to plants of potential economic importance. The team sees this as a problem primarily of original project design and a lack of clarity of objec tives, rather than as an indication of a deficiency in project management.
The project has certainly not reached sustainability as yet. As a PRIF, it is not reasonable to expect that it should do so, as a fundamental premise of a PRIF phase is that there is a probable need for a larger and longer operation al phase. Nevertheless, there are some encouraging signs that sustainability can be reached in the longer term. Some examples are:
Perhaps the most encouraging indication of long term prospects is the level of commitment apparent among the communities involved.
Stakeholder participation at the community grassroots level is the fundamental core of the PRIF project. From the evidence available, and from the team’s observations and consultations, the project is providing for very effective pa rticipation at the community level. The process and the level of achievement in this area compares very well with similar efforts in other countries that international members of the evaluation team have observed in Asia, Africa and the Pacific. The proce ss adopted, and the talents and inter-personal skills of the project personnel involved, have ensured that communities have developed a genuine sense of ownership of the process and its outputs to a much greater degree than has been the case in some simil ar programmes elsewhere.
It is important also that the community participation appears to be leading towards results that are genuinely beneficial in respect of biodiversity objectives, not just to the communities.
At a different level, other stakeholder groups and agencies have a good opportunity for input and participation through the District Conservation Committees that have been established as a result of the project.
The project is certainly making a strong contribution towards building the capacity of communities to manage and conserve their own natural resources. This is a fundamental and important achievement within the objectives of this pro ject.
What is less clear at this pilot stage is the degree to which the project is building the capacity of in-country government and non-government organisations to continue the process after international support terminates. At the national level, capacity is being increased by project funding of a new position of Biodiversity Advisor Specialist within the Ministry of Environment, Local Government and Rural Development.
In the NWFP, the implementation from within a government agency will build valuable experience and skills. In the NAs, the implementation by IUCN means that the capacity-building impact is not as direct. There are greater difficulties i n the NAs because of the political status of the area, which does not have the independent provincial status and semi-autonomous legislative powers enjoyed by the NWFP. In the NAs, there is not a specialised government agency with responsibilities for con servation and wildlife issues. A recent budget revision included a new provision to fund a high-level biodiversity coordination position within the NAs administration, and this is an important step towards building capacity. Further capacity building and institutional development within the NAs administration will be an important matter for attention in the future phase.
If the present project management arrangements in the NAs continue into the operational phase (the team is not suggesting otherwise), close attention should be paid to ensuring that long term capacity building is a key priority.
A key component of the UNDP Country Programme is a Governance Programme. This clearly has implications for capacity building at central, regional and local levels. In the future, closer links should be forged with this programme.
In the "Need for Project" section of the AIB, it is noted that "there are no incentives for rural people to maintain or manage renewable natural resources sustainably". It is noted that, although protected areas have been designated and threatened species have been identified and listed for strict protection under national and provincial laws, populations of certain species continue to decline. It suggests that "an alternative approach is needed that involves rural people in the sol ution rather than considering them the cause."
This suggests that the root causes of biodiversity loss in the mountain areas include:
The team has no reason to disagree with this definition. It also sees a related problem that there has been insufficient recognition of the ownership and stewardship rights and obligations of local communities in respect of their surrou nding natural resources.
As will be apparent from other sections of this report, the team believes that the PRIF project is showing considerable success in addressing these root causes.
As noted in 1.2, the mission team lacked a female member with experience in gender issues. In the communities of the project area, it was simply not possible for the all-male team to ask for or participate in any direct dialogue wit h women of the communities. In the NAs, we were fortunate to have the company of Razina Bilgrami, UNDP Programme Officer and Siobhan Warrington, the project’s WID Advisor. They were able to have some useful and meaningful discussion with women in some com munities. The following sections are based largely on their experiences and input. In its visit to the NWFP, the team did not have the benefit of such assistance, but we believe that the findings and principles outlined below will apply equally in the NWF P.
The PC-II for the project states that, "Where practicable women will be incorporated into the management of wild species and or habitats....To address more comprehensive issues related to population management... the project will lin k up with the appropriate agencies." However, on examining the project’s history since its inception, it is evident that gender issues have only recently begun to be incorporated in the project activities. The project was initiated in early 1995, and it was only in mid-1996 that some action was taken.
Though women were involved in the Participatory Rural Appraisal (PRA) in Khyber using AKRSP female staff as facilitators, the information gathered from them was not represented in the Village Management Plan (VMP). Women were not involv ed in the PRAs in either of the initial Baltistan sites (S-K-B) or Hushey, due to the lack of resources and the lack of Women’s Organisations in these areas.
In June 1996, a female consultant Durdana Malik was invited to consult women in three project sites, and to suggest the potential for involving women in the project. Her main conclusion was that it is important to promote the formation of WOs in the project sites as a platform for development in the village. The gender sensitisation of IUCN staff was also indicated as being a major requirement. She identified women’s immediate needs such as family planning, health and drinking water sup ply schemes. Following this research, another female consultant Rabiya Ali Khan carried out research with women in Khyber. She highlighted afforestation efforts, the development of fuel efficient stoves and the marketing of local apricot produce as possib ilities for the involvement of women in biodiversity conservation activities.
Following are the major recommendations made by both female consultants:
As a result of these recommendations, a full-time female gender specialist joined the project at the end of January 1997 as a WID Advisor, and has begun interaction with women belonging to the new valleys selected under the project. In both of the new sites (Kachura and Astore), PRAs were carried out with women with the assistance of AKRSP female staff and other local women. The results of these PRAs were incorporated into the draft VMPs prepared for these two project sites, and it is i ntended that women from the project sites will be briefed on the contents of these plans to obtain their feedback and approval. Formation of Women’s Organizations (WO’s) at village level has also been initiated with the help of AKRSP female social organis ers.
A one day gender training workshop was held for the project staff and representatives from the government forest department, as a first step to familiarise staff with the concept of gender and related issues.
Findings from Field Visits During the Evaluation Mission
Women in the Northern Areas are responsible for the majority of NRM activities in the project sites. They are responsible for daily agricultural tasks, livestock care and in some areas, for fuelwood collection and irrigation of land .
There are many differences between the project sites in terms of the natural environment, culture, language, religion, literacy rates and institutional maturity. Women’s and men’s roles and experiences therefore also differ across t he project sites.
As the need for male off-farm employment increases, women’s workload in terms of NRM at the village level is increasing. As the women themselves indicate: "The lack of fuelwood is our problem, men are always outside the village, whereas we stay in the village and have to collect fuelwood and worry about whether there is enough". The compulsion of having to go to far-off pastures for obtaining fuelwood continues to remain a major problem currently being faced by local women, and was very forcefully put across to us by all the women met.
In addition to NRM activities, women are responsible for work in the home and care of dependents, and are concerned about the social and health needs of their family. Women suffer from various health problems themselves, especially during childbirth. The collection of drinking water is claimed to be one of women’s main problems because of the heavy workload involved, especially during winter when they must also collect water for livestock. Education rates among women are very low an d in some villages there are no facilities for the education of girls.
AKRSP female staff provide strong support to the PRIF project in mobilising and ensuring the active participation of women. Without their co-operation, the task would be much more difficult.
The Need for Integrating Gender Issues
The following are suggestions about the ways in which gender issues may be better integrated in the future phase of the project.
Gender Training for Project Staff
Gender training of staff must be an on-going process. General communication skills and the concept of gender and related issues need to be dealt with in the context of the project and the communities it is working with.
Hire Local Female Staff
A capable and suitable local woman should be hired as a trainee who will in the future take the position of WID advisor. There might also be the need in the future for strengthening female field staff and also for effective linkages work.
Research and Gender Analysis
Women need to gain a higher profile in this project by ensuring that they are consulted in future research exercises, and also that their views and activities are considered and documented. Two multi-lingual local women have been tr ained in participatory research techniques, and it is intended to involve them in such research work.
Project Gender Strategy
There is an emerging need for the development of a clear gender strategy for this project. This should address activities, linkages, institutional issues and the way that women will be involved at different stages of the project cyc le. The project gender strategy will need to address the issue of women’s participation in the Village Conservation Committees and their role in decision-making regarding project activities. It is important to consult women at various stages of the projec t and especially during the preparation of the Village Management Plans.
The WID Advisor is currently undertaking the background work for this strategy. Other project staff could also provide some input. A working session with all project staff is required to be able to work through such a strategy and to se e where it is possible and realistic to involve women given the above constraints. This practical approach will be more useful than a concept paper as it will allow for follow-up. It is equally important to address this at the village level to ensure that men in the village support such a strategy. The co-operation of the men in the village is also linked to the importance male project staff give to the issue.
Social Organisation/Institutional Issues
There is a need to address this urgently and to establish how the project will work with women at the village level. As mentioned above, the WO structure does not exist in most of the sites, but there are new WOs being formed in sev eral villages. In certain communities, this would take more time due to constraints imposed by religious leaders. It may be appropriate to consider creating small interest groups of women in individual villages.
Activities Related to Biodiversity Conservation
If women are involved at different stages of the project cycle, they will be in a position to demand certain inputs and technical assistance from the project. There is a possibility to involve women directly in areas such as protect ion of natural forest, afforestation and to a lesser extent, the domestication and marketing of economic wild plants. The project will be investigating the possibilities for fuel efficient stoves, initially by consulting secondary material from existing w orking sites throughout the world and especially models which have been successful in Northern Pakistan.
Addressing Women’s Immediate Needs
It is necessary to deal simultaneously with women’s immediate social and health needs such as drinking water supply, health care (especially reproductive) and education. This can be done through effective linkages work with relevant organisations.
Project Impacts and Contributions
Despite the project being only part way through its PRIF phase, impacts at the community level are positive, with the potential for very positive results as the project proceeds to its operational phase. Indications are that the inv olved communities believe that the conservation and management of natural resources is not only the responsibility of the government but also of the community. They have developed an increasing sense of ownership of the resources and of the planning and m anagement processes.
Communities are now realising that their natural resources are a potential source of sustainable income, but have a very realistic appreciation of what is possible. As noted elsewhere, there have recently been two cases where villagers have voluntarily released back to the wild snow leopards that had been trapped in and around the villages. This is a promising indication of the attitudinal impacts of the project at community level.
In many of the project areas, the AKRSP had already done much to raise awareness and establish community institutions. The AKRSP has assisted many villages in undertaking infrastructure developments such as irrigation channels, roads, b ridges and small power stations. The PRIF project has complemented the activities of the AKRSP, and has created an awareness that the natural resources around them are very important for their own long term livelihood. As a result, some communities have b anned hunting, established penalties for violations, and adopted rules for rotating grazing.
Contribution to national efforts to conserve biodiversity
The PRIF project is making a very valuable contribution to national efforts to conserve biodiversity in Pakistan. Pakistan is a signatory to the Biodiversity Convention, and is therefore committed to the conservation of biodiversity and the sustainable use of its components. The National Conservation Strategy emphasises the need for sound conservation and management of biodiversity. More specifically, it makes provision to "promote community-based management systems so that local people participate in the protection and conservation of habitats and related wildlife species." The PRIF project is demonstrating that this is both practicable and achievable.
Previously, conventional conservation efforts in Pakistan that did not involve local communities had little success. The PRIF project is proving that a community-based approach to conservation can be beneficial both to conservation and the welfare of the communities. In a country such as Pakistan, this is very significant for the future conservation and management of natural resources.
Global Benefits and Contributions
Contribution to the larger context of GEF
The PRIF project is contributing directly to meeting GEF biodiversity objectives, and in particular to the operational programme for conservation of mountain ecosystems, through promoting conservation and sustainable use of the uniq ue mountain ecosystems of northern Pakistan. The northern area of Pakistan, the operational area of this project, is the meeting place of three of the world’s great mountain ranges, the Himalaya, Karakoram, and Hindu Kush. The project thus falls squarely within the objective of Operational Programme Number 4 (Mountain Ecosystems) as expressed in the GEF Operational Strategy which states:
"Activities in this operational programme will initially address the conservation and sustainable use of biodiversity areas under increasing pressure and imminent threat of degradation, including the Mesoamerican, Andean, Easy Africa n, and Himalayan regions."
A draft of the supporting document for Operational Programme 4 makes it clear that, for the purposes of the programme, the Himalayan region includes the Hindu Kush and Karakoram ranges. As detailed in 11.2, the operational area of t he project contains various ecosystems and species of undoubted high significance.
Perhaps just as importantly, the PRIF project is making a very important contribution to the development of techniques and processes for effective community involvement in conservation and sustainable use of biodiversity. As has been no ted elsewhere, the processes and achievements here compare very favourably with similar efforts in other parts of the world. The team is satisfied that the project is adding very significantly to the international body of experience in this very important area of endeavour.
A matter of initial concern to the team was that, with its apparent focus in some areas on species conservation and management, for example through species conservation plans, the project may not be giving sufficient attention to broade r issues of ecosystem conservation which are important in the GEF context. However, the team is satisfied that the project approach is satisfactory and realistic, and that it is in fact being effective at the ecosystem level.
For people at community level, broad concepts of biodiversity and ecosystems are difficult to understand, but they can relate to the conservation of large and visible animal species. The choice of a single species acts as a focus and ca talyst for action. In practice, the approach taken is through the protection of natural habitat and total systems rather than artificial management of species numbers. For example, one approach is to control and limit grazing of livestock on high altitude pastures, and to grow alternative forage on irrigated land at lower levels. This has general benefits for the high altitude ecosystem. As a further illustration that actions and commitments are not confined to single species management, it was interestin g and encouraging to note that all communities visited were adamant that they will not harm snow leopards, even though they are a genuine threat both to game animals and domestic livestock.
It was also encouraging to note that, in the NAs, the next major area selected for inclusion in the project is a large contiguous area encompassing several communities, with the potential to protect a large continuous ecosystem. It was suggested that it is considered to be a centre of biodiversity in the NAs, but the team was not able to ascertain for itself whether this is true.
The team believes that the project is making a very effective contribution to the objectives of the GEF, and that it is essential that it should be given the resources and opportunity to build on and consolidate the good work to date. T his will not only benefit the people and environment of the project area, but will provide important and useful lessons for application elsewhere.
Contribution to Commitments under the Convention on Biodiversity
The primary objective of the Convention on Biodiversity has three main elements:
As distinct from the many projects, both within the GEF and elsewhere, which concentrate on in-situ conservation of biodiversity in protected areas, the PRIF project is testing and demonstrating processes and techniques which rel ate to other key objectives of the Convention on Biodiversity.
The project addresses the difficult but important issue of the in-situ conservation of wild species and habitats outside protected areas through community initiatives and involvement, and this is already showing beneficial result s in terms of animal numbers in some areas. The project is also showing promise in addressing the difficult issue of sustainable use of components of biodiversity in this extreme environment.
It is exploring practical ways to address the need for equitable sharing of the benefits that might result from sustainable use of natural resources. For example, at the community level there may be future economic returns from activiti es such as ecotourism, limited trophy hunting or economically valuable plants. Careful consideration is being given to the ways in which benefits will flow into the communities. As one example, the government has already agreed that, if trophy hunting doe s occur, 75% of trophy fees will be paid directly by the client to the community concerned, with the remaining 25% going to government.
The Village Conservation Funds being developed with project support will also be an important mechanism for ensuring equitable flow of benefits within the communities.
In summary, the PRIF project is making a useful contribution to meeting the key objectives of the Convention other than the conventional in-situ conservation of biodiversity within protected areas. It thus performs a very relevan t complementary role in relation to existing and proposed protected areas management operations in Pakistan.
Application of Incremental Cost Principle
The PRIF was launched under the pilot phase of the GEF. There was therefore no specific requirement that it respect the principle of meeting incremental costs, and there was no conscious decision to take it into account. In practice , however, the PRIF provides a very good example of the application of the incremental costs principle.
The project operates in very close co-operation with the AKRSP, which is active in many aspects of rural social and economic development throughout much of the NWFP and NAs, operating within a region with a total area of over 74,000 km< SUP>2, and with an annual budget in the order of US$ 12,000,000. The AKRSP places particular focus on the building of social organisations. The AKRSP also acts as a catalyst for various other donor inputs into its area of interes t, such as in education and health services. The presence and role of the AKRSP appears to be well accepted in the villages of the region.
In effect, the PRIF project meets the incremental costs of adding the conservation and sustainable use of biodiversity to the work of the AKRSP. Physically, the PRIF project can be seen as operating in the natural and near-natural envir onment, including traditional summer grazing pastures, above the more intensely used and developed areas in and around the villages which are the AKRSP’s main focus of activity. The boundary between the two areas of interest can in many cases be considere d to be divided by the irrigation channels that many villages have constructed around the slopes above to bring water to their cultivated areas.
The degree of co-operation and synergy between AKRSP and IUCN is very encouraging and constructive. On the one hand AKRSP, as a much bigger operation, frequently provides logistical and transport support to IUCN, and can be seen as prov iding considerable co-financing support through contributions in kind. On the other hand, the village management planning processes conducted by IUCN under the PRIF have a very positive spin-off for AKRSP operations, as they take an integrated approach to the full range of conservation and development needs in the villages as a pre-cursor to identifying those aspects related to biodiversity conservation and sustainable use. In at least one area, Begusht, the two organisations have collaborated on the prep aration of a joint Natural Resources Management Plan.
Perhaps most importantly, the PRIF approach and activities start from and build on the base of the very effective village organisational structures and community processes that have been built up under the AKRSP programme. This is a key element in the undoubted success of the PRIF project to date.
There are other programmes which can be considered as part of the baseline activity underlying the PRIF activity. For example, in Swat and Chitral, the Environmental Rehabilitation Project is active. This is a programme funded by the Ne therlands Government, the World Food Programme and the Government of NWFP. Its aim is to "support Village Development Committees and Women’s Organisations to strengthen their social organisation, skills and capital formation towards sustainable village de velopment and fair sharing of natural and other resources for all sections".
In the NWFP, the project builds incrementally on the capabilities and existing baseline activities in that area.
The project is in a pilot phase, and is only recently coming to fruition. As yet, there has been little reason or opportunity to attempt to share the experiences of the project internationally. An exception is the exchange visit to Zimbabwe, although that was more concerned with acquisition of knowledge rather than imparting it.
As has been indicated elsewhere, the project is showing a high potential as a model for conservation through community involvement. The lessons are also applicable outside mountain environments. For the future, it is important that oppo rtunities are created to share the experiences and approaches with the outside world.
Leveraging of Additional Resources
In its pilot phase, the project has been aimed primarily at developing, testing and proving techniques and approaches. As yet, there has been little stress on leveraging other donor contributions to the process.
An important contribution has been the practical support that has been provided by the AKRSP. While this has not been a direct financial input, it has been nonetheless an extremely valuable contribution to the success of the project.
For the future, there is a high potential to attract other resources and make appropriate linkages as the local planning processes identify specific needs to be met. The Village Conservation Funds provide a good vehicle for the input of donor funds to meet community needs. As is discussed elsewhere, the team sees benefit in the establishment of a fund or funds focused directly on supporting biodiversity conservation and sustainable use in the northern and north-western mountain ecosyste ms of Pakistan. This would also have potential as a reliable and attractive channel for transmission of donor funds into implementing conservation programmes identified through the community planning processes.
District and provincial conservation strategies that are currently in preparation may also be a vehicle to bring the attention of potential donors to the community-based conservation approach.
In the team’s opinion, the PRIF project is fulfilling its purpose admirably. It has certainly proved the efficacy of a community-based approach to biodiversity conservation and sustainable use in the mountain areas of northern Pakis tan. It provides a very good foundation for the launching of a full-scale project. Given that the project is still only part way through the PRIF phase, and considering the great difficulties imposed by remoteness and logistics, the progress has been exce llent. Some key findings are:
The project has the potential to rank very highly among efforts worldwide to involve communities in the conservation of their resources. Indications are that it can achieve this for a comparatively modest input of resources.
The evaluation team has identified aspects where improvements can be made and lessons learnt from the experience to date. However, we see no major problems, and there is every reason to suggest that the full-scale phase should proceed w ith much the same thrust and approach as the PRIF project.
PART II:
LOOKING TO THE FUTURE
This section of the report examines the strategy and approach that might be adopted in leading from the PRIF phase to an operational GEF project.
Based on its findings and observations, the team’s fundamental approach is that the PRIF phase has more than adequately established the relevance and effectiveness of the community-based planning and management approach as a means towar ds conservation and sustainable use of biodiversity in the mountains of Pakistan. It is demonstrating a high potential to be a model that can be replicated with suitable adjustments in other parts of the world. In the team’s opinion, there is a very stron g case to move to a next phase of full operation as originally planned, subject of course to careful planning of the on-going project.
A particularly important factor is the very high level of expectation and commitment that has been built up among the communities involved. There is a potential for a major level of disappointment and loss of credibility if the good wor k cannot continue. There is also a distinct danger that the very positive progress in attitudinal change towards biodiversity protection would be reversed, with potential severe consequences for the globally significant species and ecosystems of the regio n.
The team therefore strongly recommends that an on-going operational project is approved and launched on schedule.
In regard to the design of the future phase, the team takes the approach expressed in the cliché "If it’s not broken, don’t fix it." In other words, we see no benefit in interfering with the basic thrust and approach of the core community-based activity that has been developed in the PRIF phase. Every indication is that it is relevant and effective. However, there is of course a need to examine all aspects of the design of the future project with great care to ensure that it is a s effective as possible, that it learns from the lessons of the PRIF phase, that it complies with all the necessary requirements and criteria, and that it represents efficient and effective use of GEF funds.
In the following sections, we discuss some of the issues involved. We set out a suggested concept and outline for the future phase as a basis for the more detailed planning phase which must follow, and which is beyond the scope of this present mission.
The GOP’s national strategy for conservation and sustainable use of biodiversity has four components:
The GOP is clear in "its commitment to a holistic approach to conserving biodiversity so that no single initiative by any one of the implementing agencies compromises the opportunity to obtain funds for other initiatives." This was reit erated verbally to the team.
In assessing the nature and design of the operational phase of the community-based project, it is necessary to consider its relationship with the GOP/World Bank Protected Areas Management project proposal being developed for possibl e GEF funding. As outlined above, the GOP wishes to consider all elements of GEF support for conservation and sustainable use of biodiversity as a holistic package. The team supports this approach.
The following commentary is based on consultation with World Bank and project personnel in Washington and Islamabad and on examination of some preparatory written material. There was no draft proposal for the Protected Areas proposal av ailable to the team.
The GOP/World Bank proposal plans to support the management of three existing protected areas in Pakistan. The team’s understanding is that the three have been chosen by the Biodiversity Working Group, an inter-agency committee, in coll aboration with IUCN, out of a short-list developed through an analytical process using selection criteria developed for the purpose. Of the three chosen, one is within the NWFP/NAs area which has been the operational area of the PRIF phase of the present project. This is Chitral Gol National Park in the NWFP. Unfortunately, the disruption of the team’s itinerary through weather and access problems made it impossible to visit the Chitral Gol site.
With an area of 77.5 square kilometres (30 square miles), Chitral Gol is very small in relation to the total area of the northern mountain ecosystems of Pakistan, constituting about 0.04% of the total area of the NWFP and NAs. Even assuming that activities under the proposed protected areas project extend into a broader sphere of influence with Chitral Gol as a focus, which we understand is planned, the team considers that it cannot be seen as a significant contribution to the conse rvation and sustainable use of the globally significant and diverse mountain ecosystems of northern Pakistan. It is clear that other major measures for conservation and sustainable use in this area are essential and must be pursued.
In contrast, the total area of valleys that have been selected already to participate under the PRIF project in the NWFP and NAs is 5397.5 square kilometres (2080 square miles), with potential for a major inc rease under the operational phase. Sections 3.4 and 3.5 give more detail on the geographical coverage and representation of ecosystems achieved so far. There are many additional villages anxious to participate, and it seems likely that a very high proport ion of the northern ecosystems can be brought under this style of management if sufficient resources are available (see 11.1). Based on the experience to date, the resources required are relatively modest in relation to the potential returns. While the ob jectives are of course different and it is not reasonable to claim that conservation can be as intensive as inside protected areas, the team is satisfied that the potential for overall positive impact on biodiversity in this environment is higher under th e PRIF project approach than through management of protected areas, particularly protected areas of small size.
We also have little doubt that, in biodiversity terms, the PRIF project approach will show a greater return on investment for each dollar spent. On the information available, we do not know what proportion of the proposed US$ 10 million GEF funding of the protected areas project is intended to be applied in Chitral Gol. If it comprises any significant proportion of the proposed total project budget, it will be of a similar order to the total expenditure of the PRIF project to date.
The team has noted the World Bank proposal to employ a strategy of buffer zones and "clustering of satellite core areas" to extend the conservation impact beyond the specific national park area and adjoining buffer zone. On the basis of the brief information that we have about this concept, we find it hard to envisage how it might be successfully applied in the Chitral area without conflicting with or overlapping the successful community-based activity already in progress in that area u nder the PRIF. In the Chitral district, existing and proposed project valleys under the PRIF project total approximately 1800 square kilometres. Some of these coincide with any buffer zone for Chitral Gol.
We have noted some apparent difference in perception among various officials in the World Bank and government agencies on the degree to which the project will be active beyond the boundaries of the protected areas, and also regarding th e degree of community involvement and empowerment that it will lead to in and around the protected areas.
There does appear to be a real and potentially serious issue here for the GOP to consider. In the team’s view, it is unlikely that the GEF Council will be prepared to consider either or both projects singly or together unless it is satisfied that the issues outlined above are resolved adequately. Because of the obvious overlap of functions and territory under present planning, we do not believe that it will be sufficient to simply forewarn the GEF that a further project is to come. We suggest that it is essential that there must be dialogue at a high level among the GOP, UNDP, World Bank and IUCN (in its role as an advisor to all parties) to resolve the issues before any proposal is submitted for GEF consideration. Some options to r esolve the issues are set out below:
|
|
Option |
Comments |
|
1. |
Confine the activity in the Chitral Gol component of the PA project to park management, with the community-based conservation project attending to management of the buffer zones and wider areas in the Chitral District.
|
This would require close co-operation. It should work in practice because the same NWFP officials will be in key roles in each project. |
|
2. |
Withdraw the community-based project from the whole Chitral district. |
This would be unfortunate, as there are several communities already at various stages of consultation and involvement with the PRIF project. Change would inevitably be disruptive and may lead to a loss of credibility and willingness to par ticipate. |
|
3. |
Replace Chitral Gol in the PA project with another PA from the priority list already established, with the community-based project assuming responsibility to address the issues of conservation and management in Chitral Gol. |
The team understands that the habitat in Chitral Gol is being damaged through grazing use from adjoining communities. To address this, the successor project to the PRIF could have as a priority the extension of its coverage to include the Chitral Gol valley as a project area. This would provide an opportunity to test the applicability of the community-based management approach in promoting better management of a small protected area. Another benefit of this option is that it provides an opportunity to use the PA project to address conservation needs in another type of ecosystem outside the mountains, adding to the overall coverage and effectiveness of the strategic package. In this respect also, the team would suggest that the replacement PA chosen for the PA project should not be the Indus dolphin reserve, as it is likely that this will receive protection under the forthcoming UNDP/GEF proposal on wetland conservation. |
|
4. |
Replace Chitral Gol in the PA project with a proposal to investigate, identify, create and manage a new national park designed to give firm protection to a large sample of juniper forest. |
This is a variation on Option 3. The team notes with some concern that none of the currently proposed GEF projects address the issue of conservation of the juniper forests ecosystem, although the "Biodiversity Guide to Pakistan" notes that juniper forests have been identified as one of three ecosystem types of unique ecological interest and international importance. In the team’s opinion, this option would substantially strengthen the PA proposal as a potential GEF project. |
Options 3 and 4 have the potential to provide a logical and effective national strategy for biodiversity which would include:
RECOMMENDED STRATEGY AND APPROACH
The team recommends that an operational phase project for community-based management should proceed on the following basis.
In the team’s opinion, the project should have the whole of the mountain ecosystems of the NWFP and NAs as its operational area, with specific project areas being chosen within this. The total area of these two political units is 17 4,700 square kilometres, the great majority of which falls within the mountain systems proposed as the operational area of this project. Within this broad operational area, the project will focus on identifying and working in specific project areas that c ontain fragile alpine ecosystems under threat from human use, and which contain the most important biodiversity values and species. First estimates are that the project can aim to include perhaps 20% of the broad operational area within community-managed project areas.
It has been suggested that the operational project should be extended to other areas of Pakistan or even the whole of the country. On the basis of its inspections and knowledge, the team is unable to comment on the suitability of the ap proach in other parts of the country. The team is convinced that the continuation and extension of the community approach in the mountain areas is appropriate and justified, and should be the first priority. During the preparatory phase, the GOP and UNDP may want to investigate whether the approach might be extended elsewhere, but in the team’s opinion this should not be at the expense of the mountain areas. As noted in 10, the team sees the opportunity of protecting representatives of other ecosystems of Pakistan through other elements of an integrated GEF package.
As outlined in 6.3.1, the operational area of the project is the meeting point of three of the great mountain ranges of the world, the Himalaya, Karak3333oram and Hindu Kush, which are a specific focus of GEF Operational Programme N umber 4. Northern Pakistan contains the greatest concentration of high mountain peaks in the world. In the Central Karakoram National Park alone, there are 58 peaks estimated to be over 7,000 metres in elevation. Five of the world’s peaks greater than 8,0 00 metres are within the operational area of the project.
As outlined in 3.5 and 3.6, the specific project areas already under action are providing for community-based conservation of representative samples of the full range of ecosystems of these mountain areas. In the initial feasibility pha se, pilot project areas have included approximately 5% of the total land base and the total human population in Northern Areas and Chitral.
The Western Himalaya is one of four principal areas of endemism on the Indian subcontinent attesting to the innate biodiversity value of this area. The convergence of two biogeographical provinces (Himalayan and Pamir-Karakoram) has res ulted in an impressive richness of ecological diversity based on elevation and aspect. This region of Pakistan has been identified as a centre of floral endemism with approximately 90% of the endemics occurring at altitudes over 1,200 m. There are an esti mated 2,000 medicinal plants in Pakistan, although few of them are exploited and about 90% of the country’s medicinal herb requirement is imported.
The Western Himalayan region has also been considered an Endemic Bird Area (EBA) of urgent biological importance. Breeding birds are a mixture of Palaearctic and Indomalayan forms and show the diverse origins of the avifauna. While inte nsive bird inventories of the project areas have not yet been completed, several species at risk probably occur there.
Through its selection criteria, the PRIF project focuses on areas that have high biodiversity values and that are under threat from human activities such as excessive deforestation, livestock grazing and illegal hunting particularly in the fragile high altitude ecosystems. These areas also constitute critical habitat to a number of endangered mammal species, including the markhor, snow leopard, Ladakh urial and the woolly flying squirrel. It is estimated that over 50% of the global popu lation of markhor are within the operational area of the project.
The endemic woolly flying squirrel, until recently believed to be extinct, has now been re-discovered in one part of the Northern Areas. Its global distribution is practically confined within the boundaries of the project area, where a number of other, near-threatened mammals are also known to occur (asiatic black bear, musk deer, blue sheep, grey goral, and long-tailed marmot). Of the 13 officially threatened mammal species in Pakistan (1996 IUCN Red List), at least 4 are known to occu r in one or more of the existing project valleys.
The project will address protection of fragile and threatened alpine ecosystems through community-managed conservation and sustainable use programmes and activities. These will be developed through planning and management programmes own ed by the mountain communities using innovative techniques developed during the PRIF phase. It thus will address very directly the objectives of Operational Programme 4 as outlined in the GEF Operational Strategy.
The project can thus bee seen as a focal point activity within Operational Programme 4, both in the geographical and functional senses.
The official title might be "Biodiversity Conservation and Community Development in the Mountains of Pakistan." However, as outlined in 11.5, it is recommended that a more catchy and charismatic title be adopted as a permanent ident ity.
The suggested project duration is five years. This might be broadly divided into two phases. The first three years would concentrate on consolidating the activities and building experience and would to a large extent be a continuati on of the activities under the PRIF phase. In the final two years, the emphasis would shift to the development of a long term sustainable programme and structure that learns from and consolidate the experience gained. The objective would be to leave a ful ly operational and sustainable system in place when the external support finishes. This may entail some quite major changes in organisational structures and arrangements.
An issue which deserves some consideration is the long term identity of the programme. The team noted that in the NAs, the project is closely identified with IUCN. For the communities in this area, the project is clearly seen as an IUCN project. In the NWFP, the project is centred in the Biodiversity Project Unit within the Forest and Wildlife Department of the Government of NWFP, but is identified under the official UNDP/GEF project title "Maintaining Biodiversity in Pakistan with Rural Community Development".
There is an element of inconsistency here which might be addressed in the next phase. However, a more important issue is that in the long term, the aim must be that the programme becomes sustainable and that there is no longer need for input either from IUCN or UNDP/GEF. It would therefore be desirable that the project quickly develops a permanent identity that is independent of the current organisational and funding involvement. We see benefits if this identity can be developed soon, p erhaps to coincide with the commencement of the operational phase. The aim should be that the project develops an identity in its own right, with the current funding and implementing agencies being seen as interim facilitators, each contributing in their own way towards establishing the project as a permanent entity which maintains its identity and sustainability beyond the GEF support phase.
The current official project title is obviously too cumbersome as a permanent identity. The need is for a simple but meaningful distinctive word or phrase. The team is attracted to the approach that has been adopted in various countries in Africa, where similar programmes have adopted a catchy and charismatic single word title. An example is the "CAMPFIRE" programme in Zimbabwe (Communal Areas Management Programme For Indigenous Resources). A possible example for the Pakistan programme is "IBECS" (Integrated Biodiversity Enhancement for Communities and Sustainability", pronounced "ibex", and this is used below as an illustration. However, the team stresses that this is only an illustrative example. It recommends strongly that a permanen t identity for the programme should be devised and selected through a participatory process involving the stakeholders. One approach would be to organise a regional competition in the north to develop a suitable identity and logo for the programme.
If such an identity can be devised and adopted, we suggest that all activity and organisations involved would operate under this identity. For example, all project field offices would assume this identity, regardless of the particular a gency responsible for implementation of the programme in that area. All correspondence and publications would also be under the common identity. It may be that the District Conservation Committees and any future regional bodies should also act under the c ommon title, for example as the "District IBECS Committee" and/or the "IBECS Fund."
The objectives of the PRIF phase reflected its preparatory and pilot nature. Objectives for the operational phase can be more definitive. A proposed basic objective is:
To assist and enable rural people in the mountain ecosystems of northern Pakistan to achieve conservation of their globally significant surrounding biodiversity, the sustainable use of its components and an equitable sharing of benefi ts deriving from sustainable uses.
This is designed to be directly relevant to the problems to be solved, to reflect community ownership of the resources and process, while also being directly relevant to the primary objective of the Convention on Biodiversity.
Section 4.10 suggests that the root causes of biodiversity loss in the mountain areas can be defined as:
The project must be designed to specifically address these root causes, building on the success of the PRIF project.
The implementation arrangements for the operational phase will of course be a subject for consideration and decision during the preparation process.
The team’s opinion is that, given the success of the PRIF phase, and the need to allow the agencies concerned to consolidate their achievements and their relationship with communities, there appears to be no need for fundamental changes to the present implementation arrangements. In fact, there are dangers of a loss of momentum and effectiveness if major changes are introduced at this stage of the process. We see benefit in continuing the different implementation arrangements in the NAs and NWFP in the medium term. However, one objective of the project during its life should be to draw on and integrate those different experiences to move towards a consistent, effective and sustainable organisational arrangement that can be in place when external assistance ceases.
The team cannot attempt to pre-empt these longer term decisions on permanent organisational arrangements. We suspect that the best solution will be some form of non-government or quasi-government organisation established specially for t he purpose, under direction of a board drawn widely from within the region. The existing District Conservation Committees perhaps give a hint of the type of representation that might be sought. As noted in 11.5, such a body would best operate under the id entity and logo chosen for the programme. In addition to management of the programme, it might also administer the trust fund referred to in 11.9.
The team envisages that the core activity of facilitating community conservation management should proceed essentially unchanged. This includes the valley selection process, dialogue with communities, PRAs, village management plans, conservation plans and the village conservation funds. In both the selection of project areas and in the planning processes, the on-going project should seek to place increasing emphasis on conservation of ecosystems. In the valley selection process, thi s will entail consideration of the ecosystem values of areas, and of the desirability of choosing adjoining areas to create large contiguous areas. In the planning processes, it will require attention to ensure that ecosystem and habitat conservation rema in a primary underlying objective, although this might be expressed in the form of species management plans.
Over the project period, the objective will be to extend the community planning and management processes over the greatest practicable proportion of the mountain ecosystems that meet the selection criteria. The priority should be on are as under threat or pressure from human activity, such as vulnerable high pastures used for summer grazing.
The team suggests that continuing action towards a national biodiversity fund should be kept distinct from the core thrust of this project. We note that the World Bank GEF proposal envisages the creation of a "Park Trust" to mobilis e internal and external funds to support park management activities. We also understand that there is a possibility of a trust fund aimed at combating desertification. There is an obvious need for coordination, as it seems likely that the functions of all these proposals can be integrated.
We suggest that, in the detailed planning for the operational phase project, the concept of a permanent regional biodiversity fund should be investigated. This would be aimed directly at supporting the project objectives. It would be ba sed and administered in the mountains region, under the management and direction of representatives drawn from all levels in the region. Its objective would be to attract funds and to direct them through village conservation funds to projects identified t hrough the village planning and conservation planning processes. Projects chosen would be those that can be shown to contribute directly or indirectly to the conservation and sustainable use of biodiversity.
As noted in 11.5, we suggest that such a fund should be identified directly with the biodiversity conservation programme through the use of the chosen programme identity and logo.
As noted in 3.14, the team believes that, in the operational phase project, plants of potential economic importance should be considered only to the extent that they contribute directly to the project objective. Where appropriate, t hey should be a matter for consideration within selected project areas as a social resource and as a possible source of sustainable economic return. The focus should be on assisting the communities to best realise the potential sustainable benefits. In so me cases, this might entail more detailed scientific research where there appears to be some wider commercial potential.
There may be a case for development of a more general national programme to inventory, discover and research plants and organisms of potential economic importance, perhaps on a model similar to that in Costa Rica. However, the team beli eves that it is better that this is pursued separately rather than as a part of the community-based biodiversity project.
The future project must pay close attention to capacity building, particularly in the NAs. It should be an aim that, at the end of the project period, there is an established capacity to continue the programme on a permanent and sus tainable basis without external support.
This capacity building will include but not necessarily be confined to government agencies. The team believes that, in the long term, it is likely that the programme is better managed by a special body outside the core government system (see 11.7).
The team has not yet been able to give any detailed consideration to budget requirements for the operational phase project. Taking into account the achievements under the PRIF phase, economies of scale, the project infrastructure al ready established, the efficiency of the operation to date and the benefit of the experience that has been gained, it seems likely that the planned $ 3.5 million, along with the balance of the PRIF funds not yet spent, will enable a very effective operati on.
In the PRIF phase, the percentage of project funds budgeted for direct support to projects in communities has been necessarily quite small. In the operational phase, it will be important that a greater proportion of project funds goes i n this direction.
The detailed identification and calculation of incremental costs will be an important matter for attention in the project preparation phase. The team believes that GEF criteria for incremental costs will be well met in this project. As was noted in 6.3.3, the project is already effectively operating in an incremental manner in relation to the activities of the AKRSP and other programmes.
The proposed project area is largely isolated from other parts of Pakistan by difficulties of access. Physically, it will probably be reasonable to define the system boundary for the purposes of calculating incremental costs as the boundaries of the NWFP and NAs, although more detailed investigation might show the need to adjust this to coincide more with ecosystem boundaries than political boundaries. Functionally, the system boundary might be seen to encompass the existing project s and programmes in that area that are addressing other aspects of community development and/or natural resource management. The AKRSP is the major example, but there are others.
Similarly, the baseline will presumably be the resources currently committed to community development and natural resource management across the same regions under other programmes, both government and non-government. In addition to government baseline activity, a major element will be the community development programme of the AKRSP. The forthcoming UNDP/IFAD Northern Areas Development Project may also be an important baseline component. In addition to general capacity building at the provincial government level, it will be active in on-ground development in the Diamer district, where the AKRSP is not active, but where there are proposed new areas for inclusion in the community-based conservation project.
There are some limited potential domestic economic benefits which might accrue as a result of the programme, and which might not occur otherwise, and which will therefore be a factor in incremental costs calculations. The most obvio us is the potentially large trophy hunting fees which might become available to communities if and when species numbers increase to the point that a limited trophy hunting take is acceptable and desirable as a sustainable use. Another possible source of d omestic benefits is ecotourism.
There is a strong need under GEF requirements to identify co-financing partners. This is a matter that UNDP and the GOP will need to pursue.
As noted in 6.3.3, the AKRSP can be seen as effectively providing a significant degree of co-financing through contributions in kind. Regarding other sources of support, the team suggests that emphasis should be given to establishing an d promoting the proposed regional trust fund as a vehicle for transmittal of donor funds directly to relevant projects at the community. A suggestion is that a grant is sought from another source, such as an international NGO, a bilateral donor or private foundation, to provide the seed funding for the proposed regional trust fund.
In various sections of the preceding evaluation report, there are recommendations which may influence the design and activities of the operational phase project. These should be considered in the design phase.
If the strategy outlined above is accepted, there is a need to enter the formal project preparation phase. There is provision under the GEF for the obtaining of special funding grants under the Project Development Fund (PDF) for pre paration of projects. In this case, provision to "work out the scope and modalities of the full scale project" is a component of the PRIF project.
Because the proposed operational project is largely a roll-over and quite minor adjustment of the PRIF activities, there does not appear to be the need or justification to seek PDF funding. The team believes that the necessary planning and preparatory work can readily be undertaken within the scope of the PRIF. This may require some minor re-direction of priorities for the forthcoming period, and it will be necessary to carefully plan and schedule the sequence of actions required to mov e towards submission and approval of a new GEF project brief.
In the team’s opinion, the PRIF project is performing its function very well. It is testing and proving the efficacy of the community-based approach as a means of achieving conservation and sustainable use of biodiversity in the ext reme mountain environment. It is laying a very solid foundation for a longer term operational project.
Subject to the design considerations outlined in the previous sections, the team recommends strongly that the roll-over to the full scale operational phase should proceed as planned. To do otherwise would lead to a major loss of credibi lity and a sense of disappointment among the affected communities. It would also compromise a very promising opportunity to conserve the globally significant ecosystems and species of the mountains of Pakistan.
ATTACHMENT 1
MISSION PROGRAMME
|
Monday, 7 April |
|
|
1000 |
Team assembles, meets with UNDP personnel |
|
1400 |
Team discussions |
|
|
|
|
Tuesday, 8 April |
|
|
0830 |
Meeting with IUCN project personnel |
|
1030 |
Meeting with UNDP Deputy Resident Representative and staff |
|
1200 |
Meeting with Additional Secretary, Ministry of Environment and staff |
|
1330 |
Lunch with IUCN staff (Karachi and Islamabad) and Project Director, Peshawar |
|
1430 |
Meeting with staff from IUCN Karachi |
|
1630 |
Meeting with UNDP senior staff - discussion of mission programme |
|
|
|
|
Wednesday, 9 April |
|
|
0400 |
Depart hotel for airport |
|
0600 |
Depart by air to Gilgit |
|
0700 |
Return to Islamabad (bad weather in Gilgit) |
|
0900 |
Depart for Gilgit by road |
|
2345 |
Arrive Gilgit |
|
|
|
|
Thursday, 10 April |
|
|
0800 |
Briefing on NAs project activities at IUCN Gilgit |
|
1100 |
Depart for Khyber village |
|
1530 |
Arrive Khyber village |
|
1600 |
Attend General Body meeting of Khyber village |
|
1800 |
Depart for Hunza |
|
2000 |
Arrive Hunza |
|
|
|
|
Friday, 11 April |
|
|
0800 |
Depart for Gilgit |
|
1000 |
View project video at IUCN office, Gilgit |
|
1200 |
Depart for Bagicha |
|
1530 |
Markhor sighting from road |
|
1630 |
Arrive Bagicha, meeting with community leaders, Skoyo, Krabathang, Basingo |
|
1800 |
Depart for Skardu |
|
1930 |
Arrive Skardu |
|
|
|
|
Saturday, 12 April |
|
|
0900 |
Meeting with Regional Director and staff, AKRSP |
|
1030 |
Meeting with District Commissioner, Skardu |
|
1130 |
Depart for Kachura |
|
1200 |
Attended village management planning workshop, Kachura |
|
1800 |
Depart for Skardu |
|
1900 |
Arrive at Skardu |
|
|
|
|
Sunday, 13 April |
|
|
0600 |
Depart for Hushey (Team Leader remained in Skardu for detailed consultations with IUCN staff.) |
|
1130 |
Arrive Hushey, consultation with Hushey village |
|
1500 |
Depart for Skardu |
|
2030 |
Arrive at Skardu |
|
|
|
|
Monday, 14 April |
|
|
1000 |
Flight to Islamabad canceled, depart for Besham by road |
|
1700 |
Onset of rainstorm, encountered many slips and boulders on road |
|
2000 |
Road blocked, took overnight shelter at Dassu |
|
|
|
|
Tuesday, 15 April |
|
|
1000 |
Depart for Besham |
|
1300 |
Arrive Besham, lunch with NWFP project staff |
|
1400 |
Depart for Mingora |
|
1745 |
Arrive Mingora |
|
2000 |
Dinner and discussions with project staff |
|
|
|
|
Wednesday, April 16 |
|
|
0900 |
Depart for Buner village |
|
1030 |
Arrive at Buner, consultation with local community |
|
1330 |
Depart for Mardan |
|
1530 |
Arrive Mardan, lunch with NWFP project staff |
|
1930 |
Arrive Islamabad |
|
|
|
|
Thursday, April 17 - Sunday, April 20 |
|
|
Study of background material, preparation of draft report |
|
|
|
|
|
Monday 21 April |
Consultations with UNDP, meeting with Protected Areas project formulation team, preparation of draft report |
|
Tuesday 22 April |
Meeting with NWFP project staff, preparation of draft report |
|
Wednesday 23 April |
Submission of draft report, consultations on future stage. |
|
Thursday 24 April |
Consultation meetings with World Bank, IUCN, UNDP |
|
Friday 25 April |
Revision of report |
|
Saturday 26 April |
Finalisation of report |
ATTACHMENT 2
PEOPLE CONSULTED DURING THE MISSION
The table below lists the names and positions of various people met during the course of the mission. However, perhaps the most important consultations were those with the leaders and community members of the villages vi sited by the team during its field inspections. These villages included Khaiber, Skoyo, Krabathang, Basingo, Kachura, Hushey and Buner. Unfortunately, it is not possible to list all these people by name. The team wishes to thank the many members of those communities who gave their time, and who participated in the various discussions. The team wishes also to record its thanks to those villages for the hospitality and friendship that they showed towards the team.
|
Name |
Position |
Institution |
|
Nileema Noble |
GEF Coordinator, RBAP |
UNDP, New York |
|
Eduardo Fuentes |
Principal Biodiversity Advisor, Biodiversity Management, GEF/UNDP |
UNDP, New York |
|
Thore Hansen |
Programme Manager, Country Office Support Division, RBAP |
UNDP, New York |
|
Peter Hazlewood |
Coordinator, GEF Small Grants Programme |
UNDP, New York |
|
Edythe Arturi |
RBAP/GEF |
UNDP, New York |
|
Nadim Khouri |
Agriculturalist |
Agriculture and Natural Resources Operations, Country Department 1, South Asia Region World Bank, Washington DC |
|
Malcolm Jansen |
Environmental Specialist, |
Environment and Natural Resources Division, Asia Technical Department, World Bank, Washington DC |
|
Harumi Sakaguchi |
Deputy Resident Representative |
UNDP, Pakistan |
|
Parviz Fartash |
Assistant Resident Representative |
UNDP, Pakistan |
|
Yasumitsu Doken |
Programme Officer |
UNDP, Pakistan |
|
Razina Bilgrami |
Programme Officer |
UNDP, Pakistan |
|
Farhan Sabih |
Programme Officer |
UNDP, Pakistan |
|
Dr. Chaudhry Inayatullah |
Sustainable Development Advisor |
UNDP, Pakistan |
|
Mohammad Mateen uddin |
Programme Officer |
UNDP, Pakistan |
|
Dr Javed Ahmed |
Head, Natural Resources Group |
IUCN, Islamabad |
|
Saeed-uz-Zaman |
Project Manager |
PRIF Project |
|
Shafqat Hussein |
Project Administrator |
PRIF Project |
|
Zafarullah Khan |
Additional Secretary |
Ministry of Environment, Local Government and Rural Development |
|
Mahboob Elahi |
Director General, Environment |
Ministry of Environment, Local Government and Rural Development |
|
Imram Habib |
Section Officer |
Ministry of Environment, Local Government and Rural Development |
|
Dr Mumtaz Malik |
Conservator Wildlife |
NWFP Government |
|
Aban Kabraji |
Country Representative |
IUCN Pakistan |
|
Nelma Akhund |
Head, Business and Law Unit |
IUCN Karachi |
|
Stella Jafri |
Social Strategies Group |
IUCN Karachi |
|
Scott Perkin |
Programme Support Unit |
IUCN Karachi |
|
Imtiaz Alvi |
Programme Support Unit |
IUCN Karachi |
|
Amjad Tahir Virk |
Project Coordinator |
PRIF Project, Gilgit |
|
Qasim Mehboob |
Assistant Project Coordinator |
PRIF Project, Gilgit |
|
Kent Jingfors |
Technical Advisor |
PRIF Project, Gilgit |
|
Siobhan Warrington |
WID Advisor |
PRIF Project, Gilgit |
|
Fida Hassan |
Assistant Project Coordinator |
PRIF Project, Skardu |
|
Alyoscha Gloekler |
Consultant |
PRIF Project, Gilgit |
|
Khaleel A. Tetlay |
Regional Programme Manager |
AKRSP, Skardu |
|
Aurengzeb Zia |
Agricultural Economist |
AKRSP, Skardu |
|
Dr Iqkel |
Livestock Expert |
AKRSP, Skardu |
|
|
District Commissioner |
Skardu |
|
Safdar Ali Shah |
Project Coordinator |
PRIF Project, Peshawar |
|
Abdul Hamid |
DFO (Wildlife) |
PRIF Project, NWFP |
|
Junaid Khan |
RFO (Wildlife) |
PRIF Project, NWFP |
|
Jan Wind |
Senior Technical Advisor |
Environmental Rehabilitation Project, Swat |
|
Richard Garstang |
Team Leader |
Protected Areas Project |
|
Najib Murtaza |
Projects Advisor |
World Bank, Islamabad |
|
K M Siddiqui |
Director General |
Pakistan Forest Institute |
ATTACHMENT 3
PROFILES OF COMMUNITIES WITHIN THE PROJECT
|
Region |
Project Area |
No. of Villages |
No. of House-holds |
No. of People |
Size of CCAs (ha) |
|
Northern Areas |
Khyber |
1 |
84 |
800 |
20,000 |
|
|
Hushey |
1 |
120 |
1,000 |
80,000 |
|
|
S-K-B |
3 |
150 |
1,500 |
36,000 |
|
|
Bunji |
1 |
300 |
2,500 |
30,000 |
|
|
M-D-D |
6 |
660 |
6,600 |
40,000 |
|
|
Kachura |
6 |
500 |
5,340 |
50,000 |
|
Subtotal |
|
18 |
1,814 |
17,740 |
256,000 |
|
|
|
|
|
|
|
|
NWFP |
Arkari |
11 |
600 |
4,400 |
100,000 |
|
|
Begusht |
3 |
570 |
5,400 |
50,000 |
|
|
Goleen Gol |
5 |
150 |
1,250 |
49,750 |
|
|
Keso Gol |
1 |
400 |
4,000 |
23,700 |
|
|
Nanser-Kinger Gali |
5 |
500(?) |
5,000(?) |
20,300 |
|
|
Kumrot |
3 |
750 |
7,300 |
70,000 |
|
Subtotal |
|
28 |
2,970 |
27,350 |
313,750 |
|
TOTAL |
|
46 |
4,784 |
45,090 |
569,750 |
ATTACHMENT 4
DOCUMENTS CONSULTED DURING EVALUATION
|
Author |
Title |
Date |
|
|
Village Management Plan for Sustainable Use of Natural Resources and Conservation of Biodiversity, Khaiber Valley. |
January 1996 |
|
|
Village Management Plan for Sustainable Use of Natural Resources and Conservation of Biodiversity, Arkari Valley, District Chitral. |
January, 1996 |
|
|
Ibex Conservation Plan for Arkari Valley, District Chitral. Draft |
|
|
|
Minutes- Tripartite Review Meeting for PAK/93/G41 |
September 1996 |
|
|
Biodiversity Conservation Plan for Arkari Valley, District Chitral |
|
|
Akhund, Nelma and Baqir, Fayyaz. |
Developing a National Environment Fund in Pakistan; Using Lessons Learned from the Field. UNDP/IUCN |
March, 1997. |
|
AKRSP |
Aga Khan Rural Support Programme. Thirteenth Annual Review, 1995 |
1995 |
|
AKRSP |
Operational Plan of Natural Resource Management (NRM) in Begusht Valley, Chitral |
July 1996 |
|
Alvi, Imtaz |
Developing a Monitoring and Evaluation System for the Biodiversity Project |
September 1996 |
|
Alvi, Imtaz |
Biodiversity Project, Gilgit, Field Visit Report |
|
|
Edwards, Stephen R. |
Maintaining Biodiversity in Pakistan with Rural Community Development: Second Mission Report |
November 1995 |
|
Edwards, Stephen R. |
Maintaining Biodiversity in Pakistan with Rural Community Development: Third Mission Report |
June 1996 |
|
Edwards, Stephen R. |
Maintaining Biodiversity in Pakistan with Rural Community Development: Fourth Mission Report |
December 1996 |
|
Environment and Urban Affairs Division, GOP. |
The Pakistan National Conservation Strategy |
|
|
Environment and Urban Affairs Division, Government of Pakistan. |
Maintaining Biodiversity in Pakistan with Rural Community Development. PC-II |
|
|
Environmental Rehabilitation Project. |
HUJRA (Monthly Newsletter). |
April 1997 |
|
Government of NWFP |
Notification - Policy for Trophy Hunting |
February 1997 |
|
Hushey Village Organisation (HVO) |
Ibex Conservation Plan, Hushey Valley (Ghanche District) |
March 1997 |
|
Hussein, Shafqat |
The M and E System to the Biodiversity Project |
April 1997 |
|
IUCN |
Biodiversity Action Plan And Protected Areas Management Project Inception Report |
1996 |
|
IUCN |
Wildlife Policy for Pakistan - Draft Discussion Paper |
1996 |
|
IUCN Pakistan/WWF Pakistan. |
Rapid Surveys of Short-listed Protected Areas Summary Report. |
February 1997. |
|
IUCN. |
Pakistan Biodiversity Fund: Concept/Options Paper. |
April 1997 |
|
IUCN. |
Maintaining Biodiversity in Pakistan with Rural Community Development: Annual Progress Report, January-December 1996. |
1997. |
|
Khan, Rubiya Ali |
Role of Women in the Conservation of Biodiversity, Khyber Valley, Gilgit District |
August 1996 |
|
Leaman, Dianna J. |
A Review of the Medicinal Plant Component of "Maintaining Biodiversity in Pakistan with Rural Community Development". (Draft for internal circulation only). |
March 1997. |
|
Ministry of Environment, Urban Affairs, Forestry and Wildlife. |
Strategic Approach to Financing Biodiversity Conservation in Pakistan. |
|
|
Mock, John |
Mountain Protected Areas in Pakistan |
|
|
Qureshi, Zianab. |
Pakistan Biodiversity Fund: Legal Research Paper 1, Trust Structure. |
January 1997 |
|
Roberts, T. J. |
Birds of Pakistan. |
1991 |
|
Shahi Khyber Imamabad Welfare Organisation (SKIWO) |
Ibex Conservation Plan, Khyber Valley (Gilgit District) |
March 1997 |
|
SKB Conservation Committee |
Wildlife Conservation Plan, Skoyo-Karabathing-Basingo (Skardu District) |
March 1997 |
|
UNDP |
PDF "B" Application- Protection and Management of Pakistan Wetlands |
August 1996 |
|
UNDP |
Northern Areas Development Project (NADP) - Appraisal Mission, Aide Memoire |
1997 |
|
UNDP. |
Activity Initiation Brief. Maintaining Biodiversity in Pakistan with Rural Community Development. |
|
|
Virk, Amjad, |
A Study Tour of East and Southern Africa, Trip Report, |
March 1997 |
|
Warrington, Siobhan |
Report on the Gender Workshop, IUCN Gilgit, 9 March 1997 |
April 1997 |
|
Warrington, Siobhan |
With a Pen in One Hand and a Child in the Other - Carrying Out PRA with Women in Astore and Skardu |
April 1997 |
|
World Conservation Monitoring Centre |
Biodiversity Guide to Pakistan |
1991 |